Variance BL1 - Expense Cost
Variance BL1 - Expense Cost field
The difference between the primary baseline expense cost and the at completion expense cost. Baseline variance columns only use data from visible activities. If you need to see variance for the whole project, remove any filters applied to the view.
Calculated as Primary Baseline Expense Cost minus At Completion Expense Cost.