Variance BL Project - Total Cost
Variance BL Project - Total Cost field
The difference between the baseline planned total cost and the at completion total cost. Baseline variance columns only use data from visible activities. If you need to see variance for the whole project, remove any filters applied to the view.
Calculated as Planned Total Cost minus At Completion Total Cost.