Variance BL Project - Start Date
Variance BL Project - Start Date field
The duration between the current project start date and the baseline start date. Baseline variance columns only use data from visible activities. If you need to see variance for the whole project, remove any filters applied to the view.
Calculated as Start minus BL Project Start.