Variance BL1 - Labor Cost
Variance BL1 - Labor Cost field
The difference between primary baseline labor cost and the at completion labor cost. Baseline variance columns only use data from visible activities. If you need to see variance for the whole project, remove any filters applied to the view.
Calculated as BL1 Labor Cost minus At Completion Labor Cost.