Variance BL1 - Labor Units

Variance BL1 - Labor Units field

The difference between primary baseline labor units and the at completion labor units. Baseline variance columns only use data from visible activities. If you need to see variance for the whole project, remove any filters applied to the view.

Calculated as BL1 Labor Units minus At Completion Labor Units.