Variance BL1 - Material Cost
Variance BL1 - Material Cost field
The difference between the baseline planned material cost and the at completion material cost. Baseline variance columns only use data from visible activities. If you need to see variance for the whole project, remove any filters applied to the view.
Calculated as BL1 Material Cost minus At Completion Material Cost.