Variance BL1 - Nonlabor Cost

Variance BL1 - Nonlabor Cost field

The difference between the primary baseline nonlabor cost and the at completion nonlabor cost. Baseline variance columns only use data from visible activities. If you need to see variance for the whole project, remove any filters applied to the view.

Calculated as BL1 Nonlabor Cost minus At Completion Nonlabor Cost.