Variance BL Project - Finish Date
Variance BL Project - Finish Date field
The duration between the current project finish date in the baseline project finish date. Baseline variance columns only use data from visible activities. If you need to see variance for the whole project, remove any filters applied to the view.
Calculated as Finish minus BL Project Finish.