Variance BL Project - Labor Units

Variance BL Project - Labor Units field

The difference between baseline labor units and at completion labor units. Baseline variance columns only use data from visible activities. If you need to see variance for the whole project, remove any filters applied to the view.

Calculated as BL Project Labor Units minus At Completion Labor Units.