Variance BL Project - Material Cost
Variance BL Project - Material Cost field
The difference between baseline material cost and at completion material cost. Baseline variance columns only use data from visible activities. If you need to see variance for the whole project, remove any filters applied to the view.
Calculated as BL Project Material Cost minus At Completion Material Cost.