Migrate Multiple Projects and Baselines from Primavera P6 EPPM to Oracle Primavera Cloud
- Go to the Integrations section of the project workspace.
- Activate all three integrations listed below:
- P6 to Primavera Cloud MigrateProject by CodeFilter
- P6 to Oracle Primavera Cloud Migrate Project Sync
- P6 to Primavera Cloud Migrate Project Event
To activate each integration, do the following:
- Click Actions
next to the integration, then select Activate. - In the Activate integration panel, select an appropriate Tracing level (Production, Audit, or Debug), then click the Activate button.
A message confirms that the integration has been activated. Refresh the page to view the updated status of the integration.
You can change the tracing level later by selecting Actions, and then Configure activation.
- Run the P6 to Primavera Cloud MigrateProject by CodeFilter integration.
- Click Actions
next to the integration, then select Run. - On the Configure and run page, update the following schedule parameters:
- CodeTypeName: Specify the Primavera P6 EPPM ProjectCodeTypeName to filter Projects.
- CodeValue: Specify the Primavera P6 EPPM Project Code Type Value to filter projects.
- PrjWorkspaceCode: Specify the Oracle Primavera Cloud workspace location.
- BaselineProject: Provide a value to include baselines. Valid options are Project Baseline, All Baselines and No Baseline.
- Click Run.
- Click Actions