Migrate a Single Project and Its Baselines from Primavera P6 EPPM to Oracle Primavera Cloud

For this workflow, you will activate and run the P6 to Oracle Primavera Cloud Migrate Project Sync integration.

  1. Go to the Integrations section of the project workspace.
  2. Activate the integration.
    1. Click Actions Actions icon next to the integration, then select Activate.
    2. In the Activate integration panel, select an appropriate Tracing level (Production, Audit, or Debug), then click the Activate button.

      A message confirms that the integration has been activated. Refresh the page to view the updated status of the integration.

      You can change the tracing level later by selecting Actions, and then Configure activation.

  3. Run the integration.
    1. Click Actions Actions icon next to the integration, then select Run.
    2. On the Configure and run page, update the following schedule parameters:
      • Project Code: Specify the Primavera P6 EPPM project ID filter.
      • PrjWorkspaceCode: Specify the Oracle Primavera Cloud workspace location.
      • BaselineProject: Provide a value to include baselines. Valid options are Project Baseline, All Baselines and No Baseline.
    3. Click Run.