Adding an Activity and Schedule
To schedule or reschedule activities:
-
Select the processes and then select the Add Activity & Schedule action. The Add Activity dialog box opens.
-
Select the activities and then click Ok. The Schedule Activities dialog box opens.
-
Select the scheduling method. The following choices are available:
-
Forwards from the Start Date (with non-critical Activities Starting on same date)
-
Forwards from the Start Date (with non-critical Activities Ending on same date)
-
Backwards from the end date (with non-critical Activities Starting on same date)
-
Backwards from the end date (with non-critical Activities Ending on same date)
-
Forwards from Last Completed Activity Date (with non-critical Activities Starting on same date)
-
Forwards from Last Completed Activity Date (with non-critical Activities Ending on same date)
-
-
Click Ok. A Confirmation dialog box appears.
-
Click Ok. The selected activities are added to the processes. The system calculates the start and end dates for each activity.