Auto-release Planned Orders

Instead of implementing and releasing planned orders by hand, you can enable the planning process to automatically release planned orders. During the planning run, all qualifying planned orders that fall within the release time fence will be released. Unlike manual release, you cannot modify order dates and quantities or the default implementation details.

Prerequisites

Before the planning process can release planned orders automatically, you must:

In addition, the planned orders must meet the following auto-release criteria:

Auto-release of repetitive schedules is not applicable to repetitively planned items. No material availability check is performed before WIP jobs are released.

   To enable the auto-release function:

See Also

Time Fence Control

Release Time Fence