Click to jump to parent topicUnderstanding Integration with PeopleSoft Contracts and PeopleSoft Billing

PeopleSoft Project Costing works with PeopleSoft Contracts to generate project-related customer billing. This is called rate-based project billing. For rate-based billing, PeopleSoft Contracts pulls information from project transactions and populates the PeopleSoft Billing interface tables with the billing information.

PeopleSoft Contracts stores contractual terms and conditions. You select a product with a rate price type on a contract line, associate the contract line with a project business unit and rate, optionally specify retainage and discount information for standard contracts or withholding information for government contracts, and link project activities to the contract line. In PeopleSoft Contracts, you also establish billing plans and revenue plans to manage when and how much to bill and recognize for amounts associated with one or more contract lines.

When you bill rate-based contract lines, the flow of data is controlled by PeopleSoft Contracts, and the data source is PeopleSoft Project Costing. Project Costing tracks the work performed and accumulates costs against a project, and stores the information in the Project Transaction table (PROJ_RESOURCE). Rate-based project billing is driven by applying the rates that you identified in PeopleSoft Contracts against the unbilled rows in the Project Transaction table, where the analysis types belong to the analysis group that is specified in the Billing field on the Installation Options - Project Costing page. The default analysis group is PSWKS (Billing Worksheet Grouping). PeopleSoft Billing generates invoices for the contract lines and sends information regarding the invoices back to PeopleSoft Project Costing and PeopleSoft Contracts.

You can link a contract line to a specific project activity or to all activities for that project. This enables you to link a single project with multiple activities to multiple contracts or contract lines. You can link a rate-based contract line to activities from multiple projects that are in the same project business unit. You cannot link a project activity to more than one rate-based contract or contract line.

When you bill fixed-amount, value-based, and recurring contract lines, PeopleSoft Contracts provides both the data source and the control over billing. You can associate these contract lines with a single project activity.

Note. You must associate a project activity with a contract line to use PeopleSoft Project Costing to accumulate, store, and report on project costs for contracts. For example, you must associate an activity with a contract line if you want to use the Project Transaction table as the source for rate-based project billing. You must also select one of the associated project activities for a contract line to use when creating fee and withholding transactions.

When you run the Process Project Accounting Application Engine process (PSA_ACCTGGL), the system selects those rate-based contract lines that are tied to As Incurred revenue recognition plans. For each project linked to a contract line that is associated with a selected As Incurred revenue recognition plan, the process selects the undistributed Project Transaction table rows where the analysis types are included in the PSREV analysis group. If you use the Government Contracting feature and select the Separate Billing and Revenue option on the Installation Options - Contracts page, the process selects the undistributed Project Transaction table rows where the analysis types are included in the PSREV or PSRV2 analysis groups. The system then books revenue for these projects based on the accounting rules. The exception to this rule is if you have a contract line in a government contract with a fee type of None and the Separate Billing and Revenue option is selected on the Installation Options - Contracts page. For these contract lines, the Process Project Accounting process uses the PSREV analysis group to process the revenue.

Click to jump to top of pageClick to jump to parent topicSet Up and Process Project-Related Contract Lines

This table lists the high level steps to set up and process project-related contract lines, and provides links to the PeopleBook locations that discuss the steps:

Step

PeopleBook Documentation

Set up rates.

See Defining Rate Sets and Plans.

(Optional) Set up tiered pricing.

See Defining Tiered Pricing.

(Optional) Set up rules and exceptions for organizational sharing.

See Setting Up Accounting for Projects.

Set up contracts and contract lines.

See Creating Contracts.

Assign projects and activities to contracts.

See Assigning Projects and Activities to Contracts.

See Creating and Maintaining Projects.

Accumulate and price project transactions from feeder systems.

See Understanding Pricing Project Costs.

See Integrating with Time and Labor.

See Integrating with PeopleSoft Expenses.

See Integrating with Third-Party Applications.

(Optional) Update project progress.

See Processing Project Progress.

See Percent Complete.

(Optional) Approve transactions eligible for billing.

See Summarizing Transactions for Project Manager Review.

Bill for projects.

See Processing Contracts Billing.

Recognize revenue for projects.

See The Rate-based Revenue (Accounting Rules Engine) Process (PSA_ACCTGGL).

See Processing Transactions Using Accounting Rules.

Note. You can utilize streamlined billing to reduce the number of steps for invoicing bills. Streamlined billing enables you to process transactions from PeopleSoft Contracts to PeopleSoft Billing and back to Contracts with one job.

See Also

Understanding the Relationship Between PeopleSoft Contracts and PeopleSoft Project Costing

Reviewing Billing Transactions

Streamlined Billing

Click to jump to parent topicUnderstanding the Billing Process Flow

The billing cycle diagram shows the flow of the billing process for rate-based contract lines. The numbered steps that are on the diagram correspond to updates that occur to these tables:

The numbered steps are discussed in more detail in the following diagram:

Billing cycle for rate-based contract lines

Click to jump to top of pageClick to jump to parent topicContract Limits

Costs are subject to transaction and contract line level limits. Transaction limits, which the system applies before contract line level limits, are based on limits that you establish by contract line and transaction identifier and are comprised of combinations of transaction sources, categories, and subcategories.

The system applies the transaction and contract line limits against corresponding direct and indirect cost transactions. The system creates billable transactions (rows with an analysis type of BIL) for cost transactions that completely pass limit checking or over-the-limit transactions (rows with an analysis type of OLT) for transactions that exceed applicable limits. If the Separate Billing and Revenue option on the Installation Options - Contracts page is selected, the system creates revenue transactions (rows with an analysis type of REV) for cost transactions for cost-plus contract lines that completely pass limit checking, or over-the-revenue-limit transactions (rows with an analysis type of ROL) for transactions that exceed applicable limits. The system splits cost transactions into separate billable/revenue and over-the-limit transactions in the amount of the remaining limit and excess, respectively, if the Split to Match Limit Exactly option on the Installation Options - Contracts page is selected. The system excludes OLT and ROL rows from billing and revenue processing.

The Pricing Application Engine process (PC_PRICING) calls limit processing, which examines each Project Transaction table row that represents a contract line for which you have enabled bill limits. Additionally, you can run the Limits Application Engine process (CA_LIMIT) as a stand alone process and select specific run control criteria to apply limits to specific contracts, recalculate limit amounts when totals are changed, or apply limits to billing and revenue transactions.

If a discount amount exists for a project, the transaction row amount is decreased by the discount amount prior to comparing the transaction row against the limit. Discounts do not apply to government contracts.

See Understanding the Contracts Billing Process.

Click to jump to top of pageClick to jump to parent topicContracts-Billing Interface Process (CA_BI_INTFC)

Run the Contracts-Billing Interface Application Engine process, also called the Billing Engine, in PeopleSoft Contracts for the appropriate billing methods to send Contracts-related and Project Costing-related billing activity to PeopleSoft Billing.

This process selects transaction rows (for rate-based billing methods) or billing plan lines (for fixed-amount billing methods) that are marked in PeopleSoft Contracts as ready to bill, and creates bill rows in the PeopleSoft Billing Interface tables (INTFC_BI and its related tables). After the Contracts-Billing Interface process stages billing data in these tables, the Billing Interface Application Engine process creates bills.

The PeopleSoft Enterprise Contracts 9.0 PeopleBook, "Processing PeopleSoft Enterprise Contracts Billing" chapter contains information on running the Contracts-Billing Interface process.

See Running the Contracts Billing Interface Process (CA_BI_INTFC).

See Understanding the Contracts Billing Process.

Direct Invoicing

You can select the Pre Approved and Direct Invoice billing options in the Billing Plan - Billing Plan General page in PeopleSoft Contracts to bypass the invoice approval process in PeopleSoft Billing.

Consult the PeopleSoft Enterprise Contracts 9.0 PeopleBook for information on direct invoicing and interunit billing.

See Running the Contracts Billing Interface Process (CA_BI_INTFC).

See Defining Billing Plans.

Interunit Billing

The system uses accounting rules to send data to the Contracts-Billing Interface process to forward to PeopleSoft Billing. You set up the revenue distribution and the offsetting unbilled accounts receivable (UAR) account for rate-based contract lines on the Accounting Rules page. If the general ledger business unit for the debit side of a transaction is different from the general ledger business unit for the credit side of a transaction, the system generates interunit entries when you run the Process Project Accounting process.

See Accounting Distributions for Interunit Transfers.

Click to jump to top of pageClick to jump to parent topicBilling Interface Process (BIIF0001)

The Billing Interface process can create two types of bills from the Contracts-Billing Interface process activity—temporary bills and real bills. You clear or select the Pre Approved option to create temporary or real bills for individual billing plans on the Billing Plan - Billing Plan General page in PeopleSoft Contracts.

When interfacing billing data, the system checks for billing plans that are associated with the bill rows to see if they are designated as preapproved. The system creates real bills for bill rows that are associated with preapproved billing plans. Real bills become invoices that are sent to the customer.

The system creates temporary bills for bill rows that are not associated with preapproved billing plans. Temporary bills are routed to the billing worksheet where you can review and, for rate-based bills, approve or delete the entire worksheet, or bill, defer, delete, or write-off a bill line based on your review. Temporary bills or billing worksheets are grouped by invoice and display applicable tax information.

The system updates the Project Transaction Temporary Billing table (PROJ_RES_TMP_BI) when you approve a billing worksheet with bill options of defer, over-the-limit, and write-off, since none of these actions result in creating a bill for the customer. The data exits the staging table when the Billing to Project Costing process (PC_BI_TO_PC) runs and successfully moves the data from the staging table to the Project Transaction table.

The PeopleSoft Enterprise Billing 9.0 PeopleBook, "Processing Billing Interface Activity" chapter contains information on running the Billing Interface process.

See Also

Defining Billing Plans

Using the Billing Worksheet Component

Running the Billing Interface Process (BIIF0001)

Click to jump to top of pageClick to jump to parent topicAccepting the Billing Worksheet

When you approve a billing worksheet, the system:

See Also

Using the Billing Worksheet Component

Click to jump to top of pageClick to jump to parent topicDeleting the Billing Worksheet

When you delete a billing worksheet, the system:

For fixed-amount bill rows, the system changes the Billing Plan Event Status field value to RCL (recycled) if one or more of the billing plan lines associated with the event is canceled in the billing worksheet.

Individual billing plan lines are processed if an event is marked as recycled and the billing plan line is canceled in the Contracts-Billing Cross-reference table. The Cross-reference Status field value is updated to DEL in the Contracts-Billing Cross-reference table. PeopleSoft Billing is able to process these types of rows differently because of the System Source field value (SYSTEM_SOURCE)—PBI (Project Costing to Billing Interface) for rate-based rows that originate in PeopleSoft Project Costing and CBI (Contracts to Billing Interface) for rows that originate in PeopleSoft Contracts.

Click to jump to top of pageClick to jump to parent topicBilling Finalization Process (BIIVC000)

Run the Billing Finalization process on the real bills that you created. The Billing Finalization process:

The PeopleSoft Enterprise Billing 9.0 PeopleBook discusses the fields that the Billing Finalization process updates in PeopleSoft Contracts.

See Understanding the Billing to Project Costing/Contracts Interface Process.

Note. Although only certain project activities pertain to particular contract lines, the system does not store project activities in the Contracts-Billing Cross-reference table. Activities are summarized by project and billing currency.

Click to jump to top of pageClick to jump to parent topicProject Costing-Contracts Interface Process (BIPCC000)

Run the Project Costing-Contracts Interface process after you run the Billing Finalization process. The Project Costing-Contracts process updates the Contracts-Billing Cross-reference table and the Project Transaction table with the finalized bill information from PeopleSoft Billing.

Note. Rate-based row amounts are subject to change throughout the billing process. For this reason, the system sends the rate-based rows and their final invoice amounts to the Contracts-Billing Cross-reference table only when you run the Project Costing-Contracts Interface process.

All rate-based rows and their associated discounts and retainages are written to the Project Transaction Temporary Billing table. The process includes rows with these analysis types:

The Contracts-Billing Interface process inserts fixed-amount bill rows into the Contracts-Billing Cross-reference table. This is because fixed-amount rows are not modifiable; you can only accept or delete them. The system updates the bill row status throughout the Billing Interface process, worksheet cancellation or acceptance, and the Billing Finalization process. Fixed-amount rows that specify a project are sent to PeopleSoft Project Costing with an analysis type of FBD (fixed cost billed amount).

Click to jump to top of pageClick to jump to parent topicBilling to Project Costing Process (PC_BI_TO_PC)

Run the Billing to Project Costing process for rate-based contract lines to update the Project Transaction table with results from PeopleSoft Contracts and PeopleSoft Billing processes, including adjustments, discounts, retainages, withholdings, and so forth.

PeopleSoft Billing processes write bill rows to the Project Transaction Temporary Billing table. The Billing to Project Costing process moves the rows from the Project Transaction Temporary Billing table to the Project Transaction table, either in the form of updates to existing rows or as new inserted rows. The process uses the PSBLD (Billing to Projects) analysis group to determine which rows to process and how to process the rows coming from PeopleSoft Billing.

This table lists how transactions are handled:

Description

Analysis Type of Source Transaction Row

Analysis Type of New or Updated Transaction Row

Billing Distribution Status After Billing to Project Costing Process

Bill row

BIL (billable amount)

BLD (billed amount)

D (distributed)

Write off

WTO (see note)

WTO

I (ignore)

Deferral

DEF (see note)

DEF

P (priced)

Over limit

OLT (see note)

OLT

P

Billing retainage

BRT

BRT (multiplier of -1)

P

Billing adjustment

BAJ

BAJ

D

Released billing retainage

RRT

RRT

D

Released retainage adjustment

RAJ

RAJ

D

Billing discount

DSC

DSC (multiplier of –1)

D

Prepaid bill row

BIL - with source type of CBI (Contracts to Billing Interface)

BLD

D

Prepaid utilization for billing

UTL

UTL (multiplier of –1)

I

Prepaid utilization adjustment

UAJ

UAJ (multiplier of –1)

I

Prepaid utilization adjustment

UTL

UAJ (multiplier of –1)

I

Fixed fee

BIL - with source type of CBI

BLD

D

Withholding

WTH

WTH (multiplier of –1)

D

Withholding adjustment

WAJ

WAJ (multiplier of –1)

D

Withholding release

WRL

WRL

D

Withholding release adjustment

WRJ

WRJ

D

Withholding write-off

WWO

WWO

D

Sales/use tax

SUT

SUT

D

Nonrecoverable VAT

VIN

VIN

D

Note. If the source of a WTO, DEF, or OLT row is a retainage (BRT in the Project Transaction table, or RRT in the billing worksheet) rather than a BIL, the system does not follow the logic above. Instead, the system updates the Billing Distribution Status field for the BRT row to D (distributed) and inserts three new rows: RRT row with billing distribution status of I (ignore), RAJ row with billing distribution status of I, and either a WTO row with billing distribution status of I, a DEF row with billing distribution status of P (priced), or an OLT row with billing distribution status of P.

You can determine billed and unbilled amounts by appropriately grouping analysis types within the Project Transaction table. Analysis types and analysis groups can be user-defined. PeopleSoft delivers these sample analysis groups that contain analysis types for billed and unbilled amounts:

Analysis Group

Analysis Types

BLD (billed transactions)

BAJ (billing adjustment)

BLD (billed amount)

BRT (billing retainage)

DSC (billing discount)

FBD (fixed cost billed amount)

RAJ (released retainage adjustment)

RRT (released billing retainage)

SUT (sales/use tax)

UTL (prepaid utilization for billing)

UNBLD (unbilled transactions)

BIL (billable amount)

BRT (billing retainage)

DEF (deferred amount)

OLT (over limit amount)

RRT (released billing retainage)

PSBLD (Billing to Projects)

BAJ (billing adjustment)

BIL (billable amount)

BRT (billing retainage)

DEF (billing deferral)

DSC (billing discount)

FBD (fixed cost billed amount)

OLT (over limit)

PMR (proposal management reversal)

RAJ (released retainage adjustment)

RRT (released billing retainage)

SUT (sales/use tax)

UAJ (prepaid utilization adjustment)

UTL (prepaid utilization billing)

WAJ (withholding adjustment)

WRJ (withholding release adjustment)

WRL (withholding release)

WTH (withholding)

WTO (write off)

WWO (withholding write off)

On the source transaction row, the system updates the billing distribution status to:

On the target row, the system updates the billing distribution status to:

Note. After the Billing to Project Costing process completes, run the Refresh Summary Tables Application Engine process (PC_SUM_RFSH) to synchronize the PC_SUMMARY_TBL and CA_PR_SUMM summary tables with new data in the Project Transaction table.

Click to jump to parent topicUnderstanding Data Originating from PeopleSoft Project Costing (PBI System Source)

This table shows the lifecycle of project transaction rows that are eligible for billing. This table starts after the transaction is priced:

Process

Billing Distribution Status

Cross-reference Status

Analysis Type Rows Inserted into Project Transaction Temporary Billing Table

Start

P (priced)

N/A (not applicable)

N/A

Contracts-Billing Interface (Billing Engine)

W, if action completes

S, if action aborts

N/A

N/A

Billing Interface

N/A

N/A

N/A

Accept Worksheet

N/A

N/A

OLT (over the limit)

DEF (defer)

WTO (write off)

WWO (withholding write-off)

Delete Worksheet

P

N/A

N/A

Billing Finalization

N/A

N/A

N/A

Project Costing-Contracts Interface (see note)

D (distributed)

FIN (finalized)

BAJ (billing adjustment)

BRT (billing retainage)

DSC (billing discount)

Note. The Project Costing-Contracts Interface process calls the Contracts Billing Update Application Engine process (CA_BI_UPD), which updates the Billing Plan Event Status field to DON (completed) if all rows for the event have a Cross-reference Status field value of FIN in the Contracts-Billing Cross-reference table. The system updates the Billing Plan Status field to DON if all events are completed.

Click to jump to parent topicMoving Costs and Revenue Data into PeopleSoft Project Costing

This section discusses how to summarize revenue and billing.

Click to jump to top of pageClick to jump to parent topicPages Used to Move Costs and Revenue Data into PeopleSoft Project Costing

Page Name

Object Name

Navigation

Usage

Retrieve Billing Items

PC_BI_TO_PC

Project Costing, Revenue Collection, Retrieve Billing Items, Retrieve Billing Items

Run the Billing to Project Costing process for rate-based contract lines to update the Project Transaction and summary tables with results from PeopleSoft Contracts and PeopleSoft Billing processes.

Summarize Revenue and Billing

PC_REVBI_SUM

Project Costing, Revenue Collection, Summarize Revenue and Billing, Summarize Revenue and Billing

Run the Billing and Revenue Management Application Engine process (PC_REVBI_SUM) to update the Billing and Revenue Summary table (PC_BI_MNGMT).

Retrieve Revenue from Contracts

PC_CA_TO_PC

Project Costing, Revenue Collection, Retrieve Revenue from Contract, Retrieve Revenue from Contracts

Run the Contracts to Project Costing Application Engine process (PC_CA_TO_PC) for fixed-amount contract lines to update the Project Transaction table with results from PeopleSoft Contracts and PeopleSoft Billing processes.

Click to jump to top of pageClick to jump to parent topicSummarizing Revenue and Billing

Access the Summarize Revenue and Billing page.

Use this page to update the Billing and Revenue Summary table (PC_BI_MNGMT). The system copies rows from the Project Transaction table and summarizes them by business unit, project, activity, customer, and contract number. Amounts are in transaction currencies. The process restricts the rows to analysis types that are included in the analysis groups BLD, UNBLD, PSBLD, PSREV, and PSRV2.

See Also

PeopleSoft Contracts Reports: A to Z