You can create a custom curve when you want to create and compare curves in a cash flow worksheet, but do not want to associate them with data sources of the other curve types (baseline, forecast or spends). Custom curve setup is essentially the same as setting up baseline curves.
To add a custom curve for cash flow by project/shell
1 | Open the Properties window of the cash flow detail curve. Be sure the Detail Level is Project/Shell. |
2 | Click the Curves tab. |
3 | Click Add and choose a data source that of type Custom. The Cash Flow by Project/Shell - Custom window opens. |
In this Field: |
Do This: |
|||||||||
Name |
This field is filled in automatically with the name of the data source. |
|||||||||
Type |
This field displays the curve type: Custom. |
|||||||||
Distribution |
Distribution drives how the amount value will be distributed over the time periods. Choose one:
Click the Select button. The Distribution Profiles window opens. Select a profile to use as the default profile for the curve. Note: The default profile is used for the initial display and calculations in the cash flow worksheet. You can change the distribution profile from the worksheet. If you do this, the default profile will automatically update to reflect the current selection. |
|||||||||
Cost |
Choose one:
Cost column can be chosen when creating a curve in a project or shell, but not in templates. |
|||||||||
Schedule (From Date/To Date) |
Determines what dates to start the curve and end the curve. Choose one for each:
If the these dates are changed on the Master schedule sheet, then the changes will be reflected on cash flow after the next refresh of the curves. |
To add a custom curve for cash flow by WBS
1 | Open the Properties window of the cash flow detail curve. Be sure the Detail Level is WBS (for cash flow by individual WBS codes) or Summary WBS (for summary WBS codes). |
2 | Click the Curves tab. |
3 | Click Add and choose a data source that of type Custom. The Cash Flow by Project/Shell - Custom window opens. |
4 | See the project/shell baseline curve section in Add a baseline curve for details on completing the window. |
To add a custom curve for cash flow by commitment
Custom curves are not available for cash flow by commitment.