View and manage cash flow properties

 

You can view or edit the curve properties from the Cash Flow log. You can open a view-only Properties window from the cash flow worksheet.

To edit cash flow curve properties

1 Open the project or shell and click Cost Manager > Cash Flow in the left Navigator. The Cash Flow log opens.
2 Select a curve from the log and click Properties. The Properties window opens. See Cash flow general tab and Cash flow curves tab.
3 When the Properties window is complete, click OK to save and close the window. When you save and exit the Properties window, the Cash Flow Worksheet opens for the curve you just edited.

To view cash flow curve properties from the worksheet window

1 Open the cash flow worksheet
Open the project or shell and click Cost Manager > Cash Flow in the left Navigator. Select a curve from the log and click Open, or double-click the curve.
In a base commit record, click the Cash Flow button. If a detail curve exists for the record, the cash flow worksheet opens in a view-only mode.
2 Click the View menu and choose Properties. The Properties window opens, but is not editable in this view.

Some notes on editing cash flow properties. If you edit the time scale, the period close settings will be reset, and you will need to enter new ones for the new time scale. For curves in auto mode, you can switch to manual mode and adjust the data. If you switch back to auto mode, the default profile will be used, and manual data will be overwritten.

 

 

 

 