Locking Current Period Retention on a New Subcontract
To lock retention on a new subcontract:
- Create the General Contractor Schedule of Values (SoV).
To prevent the subcontract from auto-completing, create at least two line items in the General Contractor SoV.
- Create a new subcontract. See topic Creating Subcontracts Manually.
- From the Contract Maintenance page, select the subcontractor cannot modify retention setting.
- Select the Create Contract button.
A Status page confirms the contract has been created. The Subcontractor must accept or decline the subcontract to participate on the project.
Last Published Wednesday, July 10, 2024