Creating a Future Period Planning Layout

You can plan future period resource or role assignments in the Spreadsheet view of the Assignments page. Once an assignment is in progress, if work is not being performed according to plan, you can adjust the remaining early units as necessary. Alternatively if you choose to reestimate the remaining work for an assignment, you can adjust the planned units.

To create a layout for future period planning:

  1. Click Resources.
  2. On the Resources navigation bar, click Assignments.
  3. On the Assignments page:
    1. Click Spreadsheet View.
    2. Click Customize View.
    3. In the Customize View dialog box:
    4. On the Columns tab:
      • Expand General in the Available Columns list and double-click Curve, Start, and Finish to add them to the Selected Columns list.
      • If you want to be able to assign total units to assignments which do not yet have units assigned, add the Planned Units and Remaining Early Units columns.
    5. On the Spreadsheet tab:
      • Expand Units in the Available Columns list and double-click Planned Units and Remaining Early Units to add them to the Selected Columns list.
      • If you want to be able to compare planned work against the actuals, add the Actual Units column.
      • If you want to be able to view costs related to the assignments as you plan, add the Planned Cost and Actual Cost columns.
      • Select a Timescale.
    6. Click Apply.

Tips:

Related Topics

About Resource Assignments

Future Period Planning: Troubleshooting

Future Period Planning: Settings

Future Period Planning: Entering and Editing Data

Future Period Planning: Deleting, Copying, Pasting, and Replacing Data

Future Period Planning: Updating Projects

Future Period Planning: Importing and Exporting Data

Future Period Planning: Miscellaneous Information



Legal Notices | Your Privacy Rights
Copyright © 1999, 2020

Last Published Friday, October 1, 2021