Future Period Planning: Settings

Timescale setting of the Usage Options dialog box.

When you select a smaller timescale interval from the timescale you used to enter future period values, the values you entered in the future periods are spread linearly over the smaller future periods based on the assigned calendar.

When you select a larger timescale interval, the values you originally entered in the smaller timescale intervals are aggregated into the larger intervals.

If you subsequently change the timescale back to the setting you used when you entered values in future periods, the values appear as you originally entered them.

Note: The timescale value does not affect the number of units you can assign to a future period. For example, if your timescale is set to Day, P6 will not prevent you from entering more than 24 hours.

Future period planning only supports a single line in the timescale.

Linking planned and at completion.

If the project option Link planned and at completion for not started activities is selected and you enter a value in the planned units field for a not started activity, P6 populates the remaining early units field with the same value; the reverse is also true. If this option is not selected, you can enter different values for the same future period in the planned units and remaining early units fields; in this case, the total values for each field are calculated independently for the assignment.

Activity settings.

Duration types: You can enter period values on assignments when the activity associated with the assignment has a duration type of Fixed Duration & Units or Fixed Duration and Units/Time. You cannot enter future period values for assignments to activities with a duration type of Fixed Units or Fixed Units/Time.

Activity types: You can enter period values on assignments to any type of activity except milestone activities.

Related Topics

Reference Topics

P6 Team Member Interface Field Names

Action Required for Document Reviews Toolbar

Action Required for Workflows Toolbar

Activity Count Columns of the Activity Table

Activity Steps Columns of the Activity Table

Applying Actuals Based on the Auto Compute Actuals Method

Applying Actuals Based on the Timesheets Method

Available Columns of the Activities Page

Available Columns of the Assignments Detail Window of the Activities Page

Available Columns of the Assignments Page

Available Columns of the EPS Page

Baseline Columns of the EPS Table

Bubble Chart Settings Area

Budget Columns of the EPS Table

Calendar Tab of the View Calendar Dialog Box of the Activities Page, EPS Page, Assignments Page, or Resources Page

Cost Columns of the EPS Table

Costs Columns of the Activity Table

Costs Columns of the Assignments Table

Dates Columns of the Activity Table

Dates Columns of the Assignments Table

Dates Columns of the EPS Table

Default Settings for Views

Document Search Criteria

Document Security (Reference)

Durations Columns of the Activity Table

Durations Columns of the Assignments Table

Durations Columns of the EPS Table

Earned Value Columns of the Activity Table

Earned Value Columns of the EPS Table

Errors Section of the Leveling Report Log

Future Period Planning: Deleting, Copying, Pasting, and Replacing Data

Future Period Planning: Entering and Editing Data

Future Period Planning: Importing and Exporting Data

Future Period Planning: Miscellaneous Information

Future Period Planning: Troubleshooting

Future Period Planning: Updating Projects

General Columns of the Activity Table

General Columns of the Assignments Table

General Columns of the EPS Table

Histogram Chart Settings Area

Level Resources Dialog Box (Reference)

Lists Columns of the Activity Table

Multiple Float Paths of the Activities Table

My Reviews Toolbar

My Workflows Toolbar

Number of Activities Columns of the EPS Table

Pages Supporting Filters

Percent Complete Columns of the Activity Table

Percent Complete Columns of the Assignments Table

Percent Complete Columns of the EPS Table

Performance Status Calculations

Personal Information Tab of the My Preferences Page

Pie Chart Settings Area

Portfolio Analysis Settings Area

Portfolio Analysis Toolbar

Portfolios Navigation Bar

Pre-response Thresholds (Risks)

Preferences Columns of the EPS Table

Private Documents Toolbar

My Documents Portlet Toolbar

Publication columns of the EPS Table

Recent Documents Toolbar

Resource Columns of the Assignments Table

Resources Navigation Bar

Risk Exposure (Pre-response)

Risk Exposure Calculations

Risk Scoring Method Description

Scorecard Settings Area

Set the Industry Type (P6 EPPM Only)

Standard Work Week Tab of the View Calendar Dialog Box of the Activities Page, EPS Page, Assignments Page, or Resources Page

Summary Columns of the EPS Table

Summary Tab of the View Calendar Dialog Box of the Activities Page, EPS Page, Assignments Page, or Resources Page

Team Member and P6 Mobile tab of the Consent Notice Page

Timesheet Feedback Columns of the Activity Table

Units Columns of the Activity Table

Units Columns of the Assignments Table

Units Columns of the EPS Table



Legal Notices | Your Privacy Rights
Copyright © 1999, 2020

Last Published Friday, October 1, 2021