Future Period Planning: Troubleshooting

Symptom: Future periods are uneditable.

When a future period is not eligible for editing, the spreadsheet cell is gray.

Spreadsheet cells are uneditable when any of the following is true:

Symptom: Inability to enter differing values for Planned Units and Remaining Units.

For assignments on activities that have not started, if the Link planned and at completion for not started activities option is selected on the Calculations tab of the Project Preferences, the total values of the Planned Units and Remaining Early Units for the assignment will always be equal. If this setting is not marked, you can enter different values for the same future period in the Planned Units and Remaining Early Units fields; in this case, the total values for each field are calculated independently for the assignment.

For activities that are in progress, you can always enter different future period values in the Planned Units and Remaining Early Units fields.

Symptom: Future period values have changed since they were entered.

There are many reasons why the future period values you entered for an assignment might change to different values or be placed in a different time period. For example, remaining unit data for an assignment might change when you apply actuals, or if you change the timescale in your view.

Changes to some project, activity or assignment data can cause future period values to be respread and, in some cases, recalculated. When you enter data in future periods, the values are stored in the database. When you modify activity or assignment information which causes the values to respread across future periods, the values stored in the database do not change; only the spread of those values across future periods changes. When you modify activity or assignment data which causes the values to be recalculated, the values you originally entered are recalculated according to the distribution and stored in the database; the original values are lost. If you change the financial period calendar assigned to a project, activity or assignment data might be recalculated.

Changing values in the following fields at the assignment level might respread future period values:

Changing values in the following fields at the activity level might respread future period values:

Performing the following actions might respread future period values:

Changing values in the following fields affecting Assignments might recalculate future period values:

Changing values in the following fields affecting Activities might recalculate future period values:

Related Topics

Reference Topics

P6 Team Member Interface Field Names

Action Required for Document Reviews Toolbar

Action Required for Workflows Toolbar

Activity Count Columns of the Activity Table

Activity Steps Columns of the Activity Table

Applying Actuals Based on the Auto Compute Actuals Method

Applying Actuals Based on the Timesheets Method

Available Columns of the Activities Page

Available Columns of the Assignments Detail Window of the Activities Page

Available Columns of the Assignments Page

Available Columns of the EPS Page

Baseline Columns of the EPS Table

Bubble Chart Settings Area

Budget Columns of the EPS Table

Calendar Tab of the View Calendar Dialog Box of the Activities Page, EPS Page, Assignments Page, or Resources Page

Cost Columns of the EPS Table

Costs Columns of the Activity Table

Costs Columns of the Assignments Table

Dates Columns of the Activity Table

Dates Columns of the Assignments Table

Dates Columns of the EPS Table

Default Settings for Views

Document Search Criteria

Document Security (Reference)

Durations Columns of the Activity Table

Durations Columns of the Assignments Table

Durations Columns of the EPS Table

Earned Value Columns of the Activity Table

Earned Value Columns of the EPS Table

Errors Section of the Leveling Report Log

Future Period Planning: Deleting, Copying, Pasting, and Replacing Data

Future Period Planning: Entering and Editing Data

Future Period Planning: Importing and Exporting Data

Future Period Planning: Miscellaneous Information

Future Period Planning: Settings

Future Period Planning: Updating Projects

General Columns of the Activity Table

General Columns of the Assignments Table

General Columns of the EPS Table

Histogram Chart Settings Area

Level Resources Dialog Box (Reference)

Lists Columns of the Activity Table

Multiple Float Paths of the Activities Table

My Reviews Toolbar

My Workflows Toolbar

Number of Activities Columns of the EPS Table

Pages Supporting Filters

Percent Complete Columns of the Activity Table

Percent Complete Columns of the Assignments Table

Percent Complete Columns of the EPS Table

Performance Status Calculations

Personal Information Tab of the My Preferences Page

Pie Chart Settings Area

Portfolio Analysis Settings Area

Portfolio Analysis Toolbar

Portfolios Navigation Bar

Pre-response Thresholds (Risks)

Preferences Columns of the EPS Table

Private Documents Toolbar

My Documents Portlet Toolbar

Publication columns of the EPS Table

Recent Documents Toolbar

Resource Columns of the Assignments Table

Resources Navigation Bar

Risk Exposure (Pre-response)

Risk Exposure Calculations

Risk Scoring Method Description

Scorecard Settings Area

Set the Industry Type (P6 EPPM Only)

Standard Work Week Tab of the View Calendar Dialog Box of the Activities Page, EPS Page, Assignments Page, or Resources Page

Summary Columns of the EPS Table

Summary Tab of the View Calendar Dialog Box of the Activities Page, EPS Page, Assignments Page, or Resources Page

Team Member and P6 Mobile tab of the Consent Notice Page

Timesheet Feedback Columns of the Activity Table

Units Columns of the Activity Table

Units Columns of the Assignments Table

Units Columns of the EPS Table



Legal Notices | Your Privacy Rights
Copyright © 1999, 2020

Last Published Friday, October 1, 2021