Future Period Planning: Updating Projects

Editing future periods on activities which are in progress or complete.

You can edit future period values for planned units on an assignment at any time (before or after the data date), even if the activity associated with the assignment is in progress or has an actual finish date.  

For remaining early units, you can only edit values for future periods on an assignment that fall after the data date. You cannot edit remaining early units values for period before the data date when an activity is in progress, even if you entered the values before work began on the activity. Once an activity has an actual finish date, you can not edit remaining unit values.

Note: When work on an activity is not proceeding according to plan, you can reestimate the remaining work on the assignment and update the remaining units on the assignment without changing the original plan. This allows you to compare the original baseline plan with the work that actually occurred. If the project schedule has deviated significantly from the original plan and several activities need to be re-estimated, you can update the planned units for those assignments and make another baseline for the project, or update the existing baseline.

Using Apply Actuals for assignments with manual future period values.

P6 will consider the data you entered in future periods when applying actuals if Auto Compute Actuals is selected on the activity or for the resource assigned to the activity.

Updating progress for assignments with edited future period values.

Actuals are applied to edited values for future periods on assignments depending on the way you update activity progress.

If you update activity progress by modifying the remaining units or remaining early finish on the assignment, the actual units for the activity are updated using the budgeted unit distribution you specified when you apply actuals, if the project option Recalculate actual units and cost when Duration % Complete changes is selected.

If you update activity progress by modifying the actual units on the activity or assignment, edited future period budgeted and remaining unit values are not updated when you apply actuals.

Removing progress from an activity with edited future period values.

When you remove progress from an activity that has edited future period values on an associated assignment, P6 adheres to the setting for removing progress from activities in the preferences for the project.

If Reset planned duration and units to remaining is selected the edited future period planned unit values for the assignment are respread to match the remaining unit values.

If Reset remaining duration and units to planned is selected the edited future period remaining unit values for the assignment are respread to match the planned unit values.

Earned value.

P6 will consider the data you entered in future periods when calculating earned value.

Related Topics

Reference Topics

P6 Team Member Interface Field Names

Action Required for Document Reviews Toolbar

Action Required for Workflows Toolbar

Activity Count Columns of the Activity Table

Activity Steps Columns of the Activity Table

Applying Actuals Based on the Auto Compute Actuals Method

Applying Actuals Based on the Timesheets Method

Available Columns of the Activities Page

Available Columns of the Assignments Detail Window of the Activities Page

Available Columns of the Assignments Page

Available Columns of the EPS Page

Baseline Columns of the EPS Table

Bubble Chart Settings Area

Budget Columns of the EPS Table

Calendar Tab of the View Calendar Dialog Box of the Activities Page, EPS Page, Assignments Page, or Resources Page

Cost Columns of the EPS Table

Costs Columns of the Activity Table

Costs Columns of the Assignments Table

Dates Columns of the Activity Table

Dates Columns of the Assignments Table

Dates Columns of the EPS Table

Default Settings for Views

Document Search Criteria

Document Security (Reference)

Durations Columns of the Activity Table

Durations Columns of the Assignments Table

Durations Columns of the EPS Table

Earned Value Columns of the Activity Table

Earned Value Columns of the EPS Table

Errors Section of the Leveling Report Log

Future Period Planning: Deleting, Copying, Pasting, and Replacing Data

Future Period Planning: Entering and Editing Data

Future Period Planning: Importing and Exporting Data

Future Period Planning: Miscellaneous Information

Future Period Planning: Settings

Future Period Planning: Troubleshooting

General Columns of the Activity Table

General Columns of the Assignments Table

General Columns of the EPS Table

Histogram Chart Settings Area

Level Resources Dialog Box (Reference)

Lists Columns of the Activity Table

Multiple Float Paths of the Activities Table

My Reviews Toolbar

My Workflows Toolbar

Number of Activities Columns of the EPS Table

Pages Supporting Filters

Percent Complete Columns of the Activity Table

Percent Complete Columns of the Assignments Table

Percent Complete Columns of the EPS Table

Performance Status Calculations

Personal Information Tab of the My Preferences Page

Pie Chart Settings Area

Portfolio Analysis Settings Area

Portfolio Analysis Toolbar

Portfolios Navigation Bar

Pre-response Thresholds (Risks)

Preferences Columns of the EPS Table

Private Documents Toolbar

My Documents Portlet Toolbar

Publication columns of the EPS Table

Recent Documents Toolbar

Resource Columns of the Assignments Table

Resources Navigation Bar

Risk Exposure (Pre-response)

Risk Exposure Calculations

Risk Scoring Method Description

Scorecard Settings Area

Set the Industry Type (P6 EPPM Only)

Standard Work Week Tab of the View Calendar Dialog Box of the Activities Page, EPS Page, Assignments Page, or Resources Page

Summary Columns of the EPS Table

Summary Tab of the View Calendar Dialog Box of the Activities Page, EPS Page, Assignments Page, or Resources Page

Team Member and P6 Mobile tab of the Consent Notice Page

Timesheet Feedback Columns of the Activity Table

Units Columns of the Activity Table

Units Columns of the Assignments Table

Units Columns of the EPS Table



Legal Notices | Your Privacy Rights
Copyright © 1999, 2020

Last Published Friday, October 1, 2021