In the Activity Sheets log window, click Get Data to open the Get Data window.
- Choose one of the following options:
- Click to select the All Projects field and populate the field box with all available projects. You can use the x in front of the project name to remove it from the field box.
- Click the field box to see the list of projects and then click on the project that you need.
- Select the project type: Type. You may have to scroll down, if you select all projects.
- Click OK to apply your selection and close the window.
When the Activity Sheets log window opens, you will see the following additional options on the toolbar:
- Send Data: Use this to send Unifier activity sheet data to the projects in P6. This will trigger the synchronizations at Gateway level.