Recost – Assignment Attributes

Assignment Attribute

Data Element

Calculation

Planned Cost

uuu_P6PlannedCost

Calculated at spread level.

Unifier Planned Units X Price/Unit.

If the rate source is Override, then the system uses the rate present in the activity sheet corresponding to that assignment.

Actual Cost

uuu_P6ActualCost

Calculated at spread level.

Unifier Actual Units X Price/Unit.

If the rate source is Override, then the system uses the rate present in the activity sheet corresponding to that assignment.

Remaining Cost

uuu_P6RemainingCost

Calculated at spread level.

Unifier Remaining Units X Price/Unit.

If the rate source is Override, then the system uses the rate present in the activity sheet corresponding to that assignment.

At Completion Cost

uuu_P6AtCompletionCost

Calculated at spread level.

Unifier At Completion Cost is the sum of actual cost and remaining cost for that assignment.

See Also

Attributes

Recost – Activity Attributes

WBS Attributes

Activity Attributes (General)

Activity Attributes (Scheduling)

Activity Attributes (Units)

Activity Attributes (Cost)

Activity Attributes – Earned Value

Resource Attributes

Role Attributes

Rate Sheet – Rate Tab



Legal Notices | Your Privacy Rights
Copyright © 2020

Last Published Tuesday, April 27, 2021