Assignment Attribute | Data Element | Calculation |
---|---|---|
Planned Cost |
| Calculated at spread level. Unifier Planned Units X Price/Unit. If the rate source is Override, then the system uses the rate present in the activity sheet corresponding to that assignment. |
Actual Cost |
| Calculated at spread level. Unifier Actual Units X Price/Unit. If the rate source is Override, then the system uses the rate present in the activity sheet corresponding to that assignment. |
Remaining Cost |
| Calculated at spread level. Unifier Remaining Units X Price/Unit. If the rate source is Override, then the system uses the rate present in the activity sheet corresponding to that assignment. |
At Completion Cost |
| Calculated at spread level. Unifier At Completion Cost is the sum of actual cost and remaining cost for that assignment. |