Activity Attributes (Cost)

Assignment Attribute

Data Element

Calculation

Planned Total Cost

uuu_P6PlannedTotalCost

The expected total cost of the activity, consolidating costs of all assignments.

Actual Total Cost

uuu_P6ActualTotalCost

The actual non-overtime plus overtime cost for all the resource assignments of the activity.

Remaining Total Cost

uuu_P6RemainingTotalCost

The remaining cost of all the resource assignments for the activity.

At Completion Total Cost

uuu_P6AtCompletionTotalCost

The sum of the actual costs plus remaining costs for the resource assignment on the activity. Calculated as Actual Costs plus Remaining Costs.

See Also

Attributes

Recost – Activity Attributes

Recost – Assignment Attributes

WBS Attributes

Activity Attributes (General)

Activity Attributes (Scheduling)

Activity Attributes (Units)

Activity Attributes – Earned Value

Resource Attributes

Role Attributes

Rate Sheet – Rate Tab



Legal Notices | Your Privacy Rights
Copyright © 2020

Last Published Tuesday, April 27, 2021