Activity Attributes (General)

Assignment Attribute

Data Element

Calculation

Activity ID

uuu_P6ActivityId

The unique identifier of the activity. In order to identify and track activities, P6 assigns each activity a unique Activity ID that is the result of joining the Activity ID Prefix with the Activity ID Suffix and then adding an Increment value. For example, a prefix of PROJ-A# combined with a suffix of 2500 and an Increment of 5 will yield the following activity IDs: PROJ-A#2500, PROJ-A#2505, etc.

Activity Name

uuu_P6ActivityName

The name of the activity.

Activity Status

uuu_P6ActivityStatus

The current condition of the activity. Valid values are Not Started; In Progress; and Completed.

Activity Type

uuu_P6ActivityType

Determines how duration and schedule dates are calculated for an activity. Options are:

Task Dependent: Activities are scheduled using the activity calendar rather than the calendars of assigned resources.

Resource Dependent: Activities are scheduled using the calendars of assigned resources.

Level of Effort: Activities have a duration that is determined by its dependent activities and are typically administration type.

Start or Finish Milestone: Indicates if the activity marks the beginning or end of a major stage in the project. Milestones have zero duration and no resources.

WBS Summary: Activities that are used to aggregate date, duration, and percent complete values for a group of activities that share a common WBS code level.

Activity % Complete

uuu_P6PercentComplete

An activity level setting in P6 used to update the amount of work completed on an activity. Use one of 3 options for identifying Activity Percent Complete:

Duration % Complete: Used to report progress based on Remaining Duration: [(Original Duration – Remaining Duration)/Original Duration]*100.

Units % Complete: Used to report progress based upon actual work performed and remaining units to complete: (Actual Units/At Completion Units) * 100.

Physical % Complete: Used to progress based on personal judgment.

CBS Code

bitemID

The cost code in Unifier to which you can link an activity, assignment or expense.

Performance % Complete

uuu_P6Performance%Complete

The percentage of the activity or project planned work that is currently complete. Performance % Complete is used to calculate earned value. It can be based on the technique for computing earned-value percent complete for the activity's WBS – e.g., the activity percent complete, 0/100 rule, 50/50 rule, etc.

See Also

Attributes

Recost – Activity Attributes

Recost – Assignment Attributes

WBS Attributes

Activity Attributes (Scheduling)

Activity Attributes (Units)

Activity Attributes (Cost)

Activity Attributes – Earned Value

Resource Attributes

Role Attributes

Rate Sheet – Rate Tab



Legal Notices | Your Privacy Rights
Copyright © 2020

Last Published Tuesday, April 27, 2021