Activity Sheet with Resource-Loaded and Cost-Loaded Schedules

For all of the CBS shells, the following Cash Flow curves can get data from an Activity Sheet:

When you are defining a Baseline, Forecast, and Spends Cash Flow curves (when the detail level is selected as CBS, based on the schedule type of the source project), the Activity Sheet is available as a source for:

The option is not available for Cash Flow curves when the detail level is selected as:

The Cash Flow curve properties window enables you to select to get data from:

If you select Activity Sheet, then additional options (Cost, Schedule, and Distribution) will be made available, based on the type of activity sheet that you select. In the case Resource-loaded Activity Sheet and Cost-loaded Activity Sheet, the schedule is derived from the source.

The other fields in the Cash Flow curve properties window enable you to select the distribution method and schedule for the Cash Flow curve based on the source of the Activity Sheet.

An Activity Sheet can be linked to more than one source project.

If an Activity Sheet is linked to two or more source projects, then if at least one source project is duration-based and the other source projects are resource-based, or Cost-loaded, then the other fields in the Cash Flow curve properties window will be based on resource-loaded or cost-loaded projects.

When the source project and the Activity Sheet (Activity level) are selected as source, the properties window for the Baseline Cash Flow Curve type enables you to select:

For Resource-loaded and Cost-loaded schedules, the properties window for the Baseline Cash Flow Curve type enables you to select cost, schedule, and distribution. When you select Activity Sheet, as a source, the Sheet Name drop-down field allows you to select one of the following system activity sheets, from the project activity sheets:

By default, the System Activity Sheet (Activity) option will be selected.

Note: The Baseline Cash Flow curve type will display the data from the system activity sheet, if the source is a single project.

In the properties window, the Project Type drop-down field enables you to select the following project schedules:

These options are available based on the schedules that have been received.

Note: If you do not receive a Baseline project spread, then the options above will not be displayed.

By default, the Current Project option will be selected.

When you select Activity Sheet as the source and Sheet Name as System Activity Sheet (Activity), the Cost drop-down field allows you to select the following options:

The Cost Sheet Columns option enables you to display all of the columns of the Cost Sheet. The Activity Sheet Data Sources will display the Planned, At Completion, and Remaining Costs, based on the Sheet Name that you have selected.

In the scenarios above, the Cost options are:

Use the Cost option to select one of the cost sources for the Baseline Cash Flow curve type.

By default, the Manual option is selected.

The Schedule & Distribution drop-down field displays all of the units based on the Sheet Name and the project type that you have selected. If you select the Cost as Activity Sheet Columns, then the Schedule & Distribution field drop-down will be disabled while displaying From Activity Sheet.

The Schedule & Distribution drop-down field displays the following options when you select Sheet Name as System Activity Sheet (Activity), and the Cost is selected as Cost Sheet Columns or Manual:

By default, the value in the drop-down field will be Planned Total Units.

The following table lists the various selections and results:

When Sheet Name is selected as:

Project type is selected as:

Cost options are:

Schedule & Distribution options are:

System Activity Sheet (Activity)

Current Project or Baseline Project

Activity Sheet Columns:

  • Planned Total Cost
  • At Completion Total Cost
  • Remaining Total Cost

From Activity Sheet option selected and disabled.

System Activity Sheet (Activity)

Current Project/Baseline Project

Cost Sheet Columns

Will show following options:

  • Planned Total Units
  • At Completion Total Units
  • Remaining Total Units

System Activity Sheet (Resource)

Current Project/Baseline Project

  • At Completion Cost
  • Remaining Cost
  • Planned Cost

From Activity Sheet option selected and disabled.

System Activity Sheet (Resource)

Current Project/Baseline Project

Cost Sheet Column

Will show following options:

  • At Completion Units
  • Remaining Units
  • Planned Units

The following explains Forecast Cash Flow curve properties for when the Activity Sheet is selected as a source:

The following explains Spends Cash Flow curve properties for when the Activity Sheet is selected as a source:

In the Spends Cash Flow curve properties, you can select the source of cost as Activity Sheet. The Spends Cash Flow curve properties has the following Cost and Distribution options, based on the source that you select:

The following table shows the various selections:

Sheet Name

Cost

Schedule & Distribution

System Activity Sheet (Activity)

Cost Sheet Column

Actual Total Units

System Activity Sheet (Resource)

Cost Sheet Column

Actual Units

System Activity Sheet (Activity)

Actual Total Cost

From Activity Sheet text selected and disabled.

System Activity Sheet (Resource)

Actual Cost

From Activity Sheet text selected and disabled.

If you select the Cost option, then Unifier draws the Spends Cash Flow curve by using the Actual Cost spread, Actual Start Date, and Actual Finish Date for each CBS Code, from the selected Activity Sheet.

The following topics explain the various Baseline and Forecast Budget (Cost Distribution) Cash Flow curve properties for when the Activity Sheet is selected as a source:

When you select the original source as Activity Sheet for the Baseline Cash Flow curve, the From and To dates and the spread for each CBS Code will be derived from the selected Activity Sheet and Project Type. Unifier uses the spread data from the selected Activity Sheet to draw Baseline Cash Flow curve (the period units are coming from the activity spread, and the cost will be derived either from the Cost Sheet column, or from the activity spread.

Baseline curve or Forecast curve when Schedule & distribution are derived from the Activity Sheet and Cost is derived from the Cost Sheet:

You can select the following distribution and cost sources when the data is originating from the Activity Sheet:

Distribution

Cost

Cost per CBS Code

Sheet Name: System Activity Sheet (Activity)

Project Type: Current Project

Data Source: Planned Total Units

Cost Sheet Column: Assigned Budget

Cost for each unit per CBS Code = Total cost from the Cost Sheet column/ The number of total units.

Cost for each period per CBS Code = The number of units * Cost per unit.

Example

Monthly time scale: Sample monthly unit spread for CBS Code1 which is coming from Planned Total Units in the above scenario:

 

January

February

March

April

May

June

July

CBS Code 1

100

100

100

100

100

100

100

If Total cost per CBS Code1 = $70000, then the cost per unit = $70000/700 = $100 and cost per period will be = 100 * $100 = $10000

Monthly time scale: Sample cost spread for CBS Code1 for each period will be calculated as follows:

 

January

February

March

April

May

June

July

CBS Code 1

$10000

$10000

$10000

$10000

$10000

$10000

$10000

The above Cost spread sample will be distributed in the Baseline Cash Flow curve. If the user selects Sheet Name: Activity Sheet (Resource level), with resource units selected as distribution source, and the cost source is coming from the Cost Sheet column, then sum all of the Planned units for each CBS Code by day which it will be used to distribute the costs. The Cost per unit will be calculated as shown above. The user should be able to select the units spread from either the current project or the Baseline. The cost distribution will be done in the similar way (as shown above) for the other time periods such as yearly scale or financial periods.

Baseline curve or Forecast curve when Schedule & distribution and cost are derived from the Activity Sheet:

You can select the following distribution and cost sources for the data that is originating from the Activity Sheet:

Distribution

Cost

Cost for each unit per CBS Code

Sheet Name: System Activity Sheet (Activity)

Project Type: Current Project

Data Source: Planned Total Cost

Cost in this case is coming from Planned Total Cost spread data at Activity level for each CBS Code.

The cost will be calculated in the source Activity Sheet itself using the units and assigned role or resource rate at Activity level.

Cost for each period per CBS Code: Sum of all planned costs for each CBS Code at activity level.

The sample cost spread for the CBS Code 1, when the selected Planned Total Cost in the above scenario is as follows:

Note: In this case, the cost spread data will be received from the selected Activity Sheet (either from current project or Baseline).

 

January

February

March

April

May

June

July

CBS Code 1

$100

$100

$100

$100

$100

$100

$100

If you select the new distribution and cost options from the Activity Sheet, then:

Baseline curve or Forecast worksheet when Schedule, distribution, and cost are derived from the Activity Sheet:

For each CBS Code in the Baseline or Forecast worksheet, when the source is selected as Activity Sheet:

Spends Curve and Data Distribution

The following explains:

When both cost and distribution is coming from Activity Sheet

You can define the Spends curve to get the actuals spread data from the Activity Sheet for the Resource loaded or Cost loaded projects. When you select the Activity Sheet as a source for the Spends curve, Unifier will derive the distribution and actual costs from the Activity Sheet. The actual spread data will be coming from the current project.

The From Date and To Date fields are displayed according to the values of the earlier Actual Start Date and Date which is across the activities, per CBS Code for In progress activities. The From Date and To Date fields are read-only.

Note: The Data Date field value can be in the past, current, or in the future. The Actuals are always shown, until the date of the Data.

The Actuals in periods show the spread data coming from the Activity Sheet that you have selected.

The distribution data is read-only.

The Actual spread data as of the data date is displayed in the Forecast curve worksheet if in the Forecast curve properties, the curve is set to begin at the end of the actuals.

The graph shows both the actuals (cumulative and incremental values).

The Actual spread data per CBS Code will be until the data date. For example, if the Actual Start is 02/10/2020 and Data Date is 08/15/2020, then the Actuals cost spread will be shown until the data date (08/15/2020), in the worksheet.

 

From Date

To Date

Feb

Mar

Apr

May

Jun

Jul

Aug

CBS Code 1

02/10/2020

08/15/2020

$100

$100

$100

$100

$100

$100

$100

Forecast with Actuals

When you select the source as Remaining Total Cost, or Remaining Total Units, the remaining spread data will be used as source for the Forecast curve. The Actuals will be seen as of data date, and the remaining spread will start from the data date. For example, in the table above, the month of August will show the Actuals as of date + remaining Forecast data ($700 + $100).

 

From Date

To Date

Aug

Sep

Oct

Nov

Dec

Jan

Feb

Mar

Apr

CBS Code 1

08/15/2020

04/15/2021

$800

$100

$100

$100

$100

$100

$100

$100

$100

When the total actual cost is derived from cost sheet and schedule/distribution is derived from Activity Sheet

You can receive the Actual spread units from the Activity Sheet, and the total payment amount from the Cost Sheet column. In this case, the Actual cost can be calculated as the number of actual units * actual cost per unit. See the following example for the monthly time scale:

 

January

February

CBS Code 1

50

10

CBS Code 2

0

20

In this example, if the total actual cost (received from the Cost Sheet column) for CBS Code 1 is $6000, and the CBS Code 2 is $1000, then the actual cost per unit will be as follows:

 

January

February

CBS Code 1

$50000

$1000

CBS Code 2

 

$1000

Additional Information:

See Also

Introduction

Configuring the Gateway Integration

Mapping P6 Projects in Shell Details

Master Rate Sheet

Activity Manager

About Unifier and P6 Integration

About Unifier and Oracle Primavera Cloud Integration

Source Application Link in Activity Sheet

Activity Sheet Created from P6 through Gateway

Activity Sheet Created from Oracle Primavera Cloud Project through Gateway

Unifier Activity Manager for Oracle Primavera Cloud Schedules

Using Activity Sheet Data to Track Baseline, Forecast, and Spends in Cash Flow

P6 Activity Picker in Business Process or Shell Details

Earned Value Manager

Permissions

Attributes

Templates

Configuration Package

Copyright



Legal Notices | Your Privacy Rights
Copyright © 2020

Last Published Tuesday, April 27, 2021