This Activity in the Project Network Diagram Section
This Activity in the Project Network Diagram displays a network of activities and resources that are directly impacted by this activity. Each node represents an activity() or Resource (
). The size of an activity node represents the planned duration (large, medium, or small). The color intensity of an activity indicates the extent of predicted delay for that activity where:
- Grey indicates no delay (delay metric value = 0)
- Amber indicates medium predicted delay (30<= delay metric >= 70)
- Red indicates a large predicted delay (delay metric value > 70)
Click on a specific node (activity) in the network diagram to view the Successor activities, Predecessor activities, and the Actions tab associated with that activity
Related Topics
Factors Considered in Predicting Activity Delay Section
Last Published Tuesday, December 24, 2024