Delay Predictions Section
The Delay predictions section displays displays the likelihood of the activity being delayed by 20% of its planned duration. Additionally, it also shows the potential delays at 10%, 50%, and 90% likelihood.
For example, there is a 10% likelihood of the activity being delayed by more than 144 days, whereas there is a 90% likelihood that the activity will be delayed by 1 day.
Select View prediction details to access the Delay Predictions Page.