Overview Section
The Overview section displays details of the selected activity:
- Activity status: The current status of the activity. Choices include: In progress, Not started, or Completed.
- Associated scheduling issues: The number of scheduling issues this activity is associated with as per the Scheduling Assessment section.
- Activity type: The classification of the activity. An activity can be classified as resource dependent, task dependent etc.
- Primary resource: The name of the primary resource associated with the activity.
- Other resources: All other resources associated with the activity.
- Planned duration: The length of the activity as determined by the current project schedule. In the above example, the Planned duration of the activity is 41 days.
- Actually completed: The percentage of the activity currently completed, expressed in days and percents.
- Activity late by: The number of days by which the activity is currently delayed. If the planned end date is greater than the baseline end date, then the delay is calculated as (Planned end date - Baseline end date). Otherwise it is not delayed (zero days).
The Activity Dates section displays a bar chart to display the difference between your project's Planned date, Baseline date, and the Predicted date by CIC Advisor.
Click View similar activities to view similar activities in other projects on the Activity Discovery Page.