Activity Discovery Page

How to Get Here

  1. Sign in to Construction Intelligence Cloud Advisor.
  2. On the Project Listings page, select the Predicted delay likelihood KPI of a project.
  3. On the Schedule Intelligence page, click More details in the Activity Delay section.
  4. On the Activities page, select a specific rectangle or WBS on the heat map.
  5. In the side panel, select the Actions tab and then click Discover similar activities.

    Activity Discovery Page of Construction Intelligence Cloud

How to Use this Page

The Activity Discovery page allows you to evaluate the performance of a specific activity in your project in comparison to similar activities identified from past projects. Use this page to evaluate the following questions:

This page contains the following sections:

Section Number

Section Title

1

Activity Delay Section

2

Filters Pane

Related Topics

Project Schedule Module Overview

Activity Delay Section

Filters Pane

Schedule Intelligence Page

Delay Predictions Page

Key Factor Recommendations

Schedule Assessment Page

Schedule Assessment Page-New!

Activities Page

Project Delivery Network Page

Activity Network Page

Activity Details Page

Benchmarking Page

Benchmarking Page - New!

Benchmarking Details Page



Last Published Tuesday, December 24, 2024