Project Delivery Network Page
How to Get Here
- Sign in to CIC Advisor.
- Select any of the following links to access the Activities page:
- On the Project Listings page, select the Predicted delay activities KPI of a project.
- On the Schedule Intelligence page, click More details in the Activity delay section.
- On the Activities page, click Project Delivery.
How to Use this Page
The Project Delivery Network page provides a visual of the project schedule you created as a network of activities, resources, and milestones in your construction project. Each node represents an activity() or resource (). The size of an activity node represents the planned duration (large, medium, or small). The color intensity of an activity indicates the extent of predicted delay for that activity where:
- Grey indicates no delay
- Amber indicates medium predicted delay
- Red indicates a large predicted delay
Use the network diagram to
- understand how a project delay or delivery on time impacts the risk on predecessor or successor activities
- identify critical path activities () and resources in your project
- identify how many activities have been completed ()
- identify how many activities have not been completed ()
- identify activities with a large predicted delay, no predicted delay, and vital activities ()
- identify activity milestones () in your project
To focus on a specific aspect of your project plan, select any of the following tabs:
- Incomplete Activities: View incomplete activities in your project with predicted delay evaluated for each activity.
- Activities starting in the next 30 days: View the successor activities that are due to begin in the next 30 days with the predicted delay evaluated for each activity.
- Critical Path Activities: View only the resources and activities included in the critical path of the project.
- Vital Activities: View only those activities that impact several other activities with the predicted delay evaluated for each activity.
- Vital Resources: View only those resources that are associated with activities and milestones that are crucial for completing the project. with the predicted delay.
- Click Refresh to view the default project delivery network diagram generated for your project
- To locate a specific activity or resource, enter the name of an activity or resource in the search bar and then select Search .
- Hover your cursor over a specific activity or node to view details.
- Click on an activity node to view details of its predecessor and successor activities
- Click on a resource node to view the activities assigned to the resource.
Related Topics
Project Schedule Module Overview
Last Published Thursday, December 7, 2023