Activity Network Page
How to Get Here
- Sign in to Construction Intelligence Cloud Advisor.
- Select any of the following links to access the Activities page:
- On the Project Listings page, select the Predicted delay activities KPI of a project or
- On the Schedule Intelligence page, click More details in the Activity delay section.
- On the Activities page, drill-down through the WBSs and select an activity on the heat map.
- Select the Actions tab and click View activity within project delivery network.
How to Use this Page
The Activity Network page provides a visual of the project schedule you created as a network of activities, resources, and milestones in your construction project. Each node represents an activity() or Resource (). The size of an activity node represents the planned duration (large, medium, or small). The color intensity of an activity indicates the extent of predicted delay for that activity where:
- Grey indicates no delay (delay metric value = 0)
- Amber indicates medium predicted delay (30<= delay metric >= 70)
- Red indicates a large predicted delay (delay metric value > 70)
Use the network diagram to
- understand how a project delay or delivery on time impacts the risk on predecessor or successor activities
- identify critical path activities () and resources in your project
- identify how many activities have been completed ()
- identify how many activities have not been completed ()
- identify activities with a large predicted delay, no predicted delay, and vital activities
- identify activity milestones () in your project
Click on a specific node (activity) in the network diagram to view the Successor activities, Predecessor activities, and the Actions tab associated with that activity as show above.
To focus on a specific aspect of your project plan, select any of the following tabs:
- Incomplete Activities: View incomplete activities in your project with predicted delay evaluated for each activity.
- Activities starting in the next 30 days: View the successor activities that are due to begin in the next 30 days with the predicted delay evaluated for each activity.
- Critical Path Activities: View only the resources and activities included in the critical path of the project.
- Vital Activities: View only those activities that impact several other activities with the predicted delay evaluated for each activity.
- Vital Resources: View only those resources who are critical for several activities.
This page includes the following sections:
Section Number | Section Title |
---|---|
1 | Project Network Diagram (described above) |
2 | |
3 | |
4 |
Related Topics
Project Schedule Module Overview
Last Published Thursday, December 7, 2023