P6 - Burn Down / Primavera - Burn Down

Description: Use this subject area to analyze daily project performance through burn down charts and schedule adherence metrics. Metrics include planned, actual, remaining, and emergent counts and units. Emergent data is from activities which were added after burn down began. This subject area requires project specific UDF configuration in P6.

Folder

Subfolder

Field Name

Dimension/ Fact / Lookup

Description

Values Derived From / Calculated By

Project

Budget - (Project)

 

 

Project Budget

 

Project

Budget - (Project)

Current Budget

Dimension

The Current Budget is the sum of the Original Budget and all approved budget changes in the Budget Change Log.

Value Derived From : Dim_W_PROJECT_HD_ID.CURRENT_BUDGET

Project

Budget - (Project)

Current Variance

Dimension

Computed as the Current Budget minus the Total Spending Plan. Not rolled up.

Value Derived From : Dim_W_PROJECT_HD_ID.CURRENT_VARIANCE

Project

Budget - (Project)

Distributed Current Budget

Dimension

Computed as sum of the Current Budget values from one level lower. Not rolled up.

Value Derived From : Dim_W_PROJECT_HD_ID.DISTRIBUTED_CURRENT_BUDGET

Project

Budget - (Project)

Original Budget

Dimension

Original budget for the project.

Value Derived From : Dim_W_PROJECT_HD_ID.ORIGINAL_BUDGET

Project

Budget - (Project)

Proposed Budget

Dimension

The Proposed Budget is the sum of the Original Budget plus the Approved and Pending budgets from the budget change log. Not rolled up.

Value Derived From : Dim_W_PROJECT_HD_ID.PROPOSED_BUDGET

Project

Budget - (Project)

Total Benefit Plan

Dimension

Sum of the Monthly Benefit Plan. Not rolled up.

Value Derived From : Dim_W_PROJECT_HD_ID.TOTAL_BENEFIT_PLAN

Project

Budget - (Project)

Total Benefit Plan Tally

Dimension

Sum of the Monthly Benefit Plan Tally. Not rolled up.

Value Derived From : Dim_W_PROJECT_HD_ID.TOTAL_BENEFIT_PLAN_TALLY

Project

Budget - (Project)

Total Funding

Dimension

The total amount of funding contributed to the project by your funding sources.

Value Derived From : Dim_W_PROJECT_HD_ID.TOTAL_FUNDING

Project

Budget - (Project)

Total Spending Plan

Dimension

Sum of the Monthly Spending Plan. Not rolled up.

Value Derived From : Dim_W_PROJECT_HD_ID.TOTAL_SPENDING_PLAN

Project

Budget - (Project)

Total Spending Plan Tally

Dimension

Sum of the Monthly Spending Plan Tally. Not rolled up.

Value Derived From : Dim_W_PROJECT_HD_ID.TOTAL_SPENDING_PLAN_TALLY

Project

Budget - (Project)

Unallocated Budget

Dimension

Calculated as Total Current Budget - Distributed Current Budget.

Value Derived From : Dim_W_PROJECT_HD_ID.UNALLOCATED_BUDGET

Project

Budget - (Project)

Undistributed Current Variance

Dimension

Computed as the Total Spending Plan minus the Total Spending Plan Tally. Not rolled up.

Value Derived From : Dim_W_PROJECT_HD_ID.UNDISTRIBUTED_CURRENT_VARIANCE

Project

Dates - (Project)

 

 

Project Dates

 

Project

Dates - (Project)

Anticipated Finish

Dimension

Anticipated finish date of WBS, Project and EPS elements. User-entered - not dependent upon any other fields. If there are no children, the anticipated finish date will be the Finish date displayed in the columns.

Value Derived From : Dim_W_PROJECT_D_Project.ANTICIPATED_FINISH_DATE

Project

Dates - (Project)

Anticipated Start

Dimension

Anticipated start date of WBS, Project and EPS elements. User-entered - not dependent upon any other fields. If there are no children, the anticipated start date will be the Start date displayed in the columns.

Value Derived From : Dim_W_PROJECT_D_Project.ANTICIPATED_START_DATE

Project

Dates - (Project)

Data Date

Dimension

The current data date for the project. The project status is up to date as of the data date. The data date is modified when project actuals are applied.

Value Derived From : Dim_W_PROJECT_D_Project.DATA_DATE

Project

Dates - (Project)

Date Added

Dimension

The date this activity was inserted.

Value Derived From : Dim_W_PROJECT_D_Project.ADD_DATE

Project

Dates - (Project)

Finish

Dimension

The current finish date of the activity. Set to the activity remaining early finish date while the activity is not started or in progress, and the actual finish date once the activity is completed.

Value Derived From : Dim_W_PROJECT_D_Project.PROJECT_FINISH_DATE

Project

Dates - (Project)

Forecast Finish Date

Dimension

An alternate end date to be optionally used by the scheduler (see Schedule dialog), which is set by the user by dragging the project bar in the Gantt Chart around while manually leveling the resource profile (in a resource analysis layout, tracking or PA). In User Preferences dialog, the user can choose to view remaining units for a resource based on the forecast dates or the remaining dates.

Value Derived From : Dim_W_PROJECT_D_Project.FORECAST_FINISH_DATE

Project

Dates - (Project)

Forecast Start Date

Dimension

An alternate start date to be optionally used by the scheduler (see Schedule dialog), which is set by the user by dragging the project bar in the Gantt Chart around while manually leveling the resource profile (in a resource analysis layout, tracking or PA). In the User Preferences dialog, the user can choose to view remaining units for a resource based on the forecast dates or the remaining dates.

Value Derived From : Dim_W_PROJECT_D_Project.FORECAST_START_DATE

Project

Dates - (Project)

Must Finish By

Dimension

The date by which all project activities must finish. If entered, it is used as the project late finish date by the project scheduler.

Value Derived From : Dim_W_PROJECT_D_Project.PROJECT_PLANNED_FINISH_DATE

Project

Dates - (Project)

Planned Start

Dimension

The date the activity is scheduled to begin. This date is computed by the project scheduler but can be updated manually by the project manager. This date is not changed by the project scheduler after the activity has been started.

Value Derived From : Dim_W_PROJECT_D_Project.PLANNED_START_DATE

Project

Dates - (Project)

Scheduled Finish

Dimension

The early finish date of the latest activity in the project, as computed by the project scheduler.

Value Derived From : Dim_W_PROJECT_D_Project.SCHEDULED_FINISH_DATE

Project

Dates - (Project)

Start

Dimension

The current start date of the activity. Set to the activity remaining early start date while the activity is not started, and the actual start date once the activity is started.

Value Derived From : Dim_W_PROJECT_D_Project.PROJECT_START_DATE

Project

Dates - (Project)

Workdown Date

Dimension

The date as specified in the Project level UDF sys_workdown_date

Value Derived From : Dim_W_PROJECT_HD_ID.WORKDOWN_DATE

Project

Durations - (Project)

 

 

Project Durations

 

Project

Durations - (Project)

Actual Duration

Dimension

Actual duration is the total time from the project actual start date to the actual finish date (for completed projects), or to the current data date (for in-progress projects).

Value Derived From : Dim_W_PROJECT_D_Project.ACTUAL_DURATION

Project

Durations - (Project)

At Completion Duration

Dimension

The duration at completion is the total time from the project current start date to the current finish date.

Value Derived From : Dim_W_PROJECT_D_Project.AT_COMPLETION_DURATION

Project

Durations - (Project)

Baseline Project Duration

Dimension

The duration of the baseline project.

Value Derived From : Dim_W_PROJECT_D_Project.BASELINE_DURATION

Project

Durations - (Project)

Planned Duration

Dimension

Planned duration is the total time from the project planned start date to the planned finish date.

Value Derived From : Dim_W_PROJECT_D_Project.PLANNED_DURATION

Project

Durations - (Project)

Remaining Duration

Dimension

Remaining duration is the total time from the current data date date to the current finish date.

Value Derived From : Dim_W_PROJECT_D_Project.REMAINING_DURATION

Project

Durations - (Project)

Variance - Baseline Project Duration

Dimension

The duration between the baseline project duration and the current project duration. Calculated as Planned Duration minus At Completion Duration.

Value Derived From : Dim_W_PROJECT_D_Project.DURATION_VARIANCE

Project

General - (Project)

 

 

General Project Information

 

Project

General - (Project)

Added By

Dimension

The name of the user who added the project

Value Derived From : Dim_W_PROJECT_HD_ID.ADDED_BY_NAME

Project

General - (Project)

Datasource Id

Dimension

A unique source Id created for the Primavera data source being used. Used to identify data sources when using multiple Primavera data sources.

Value Derived From : Dim_W_PROJECT_HD_ID.DATASOURCE_ID

Project

General - (Project)

Project Leveling Priority

Dimension

Priority for leveling

Value Derived From : Dim_W_PROJECT_HD_ID.PROJECT_PRIORITY

Project

General - (Project)

Project Score

Dimension

The Project score

Value Derived From : Dim_W_PROJECT_HD_ID.OVERALL_PROJECT_SCORE

Project

General - (Project)

Project Description

Dimension

The project description

Value Derived From : Dim_W_PROJECT_HD_ID.PROJECT_DESCRIPTION

Project

General - (Project)

Project Id

Dimension

The Project Id of the project

Value Derived From : Dim_W_PROJECT_HD_ID.PROJECT_ID

Project

General - (Project)

Project Name

Dimension

The project name

Value Derived From : Dim_W_PROJECT_HD_ID.PROJECT_NAME

Project

General - (Project)

Unique Project ID

Dimension

The Unique ID of the project

Value Derived From : Dim_W_PROJECT_HD_ID.PROJECT_ID

Project

General - (Project)

Strategic Priority

Dimension

Resource designated as owner of the project

Value Derived From : Dim_W_PROJECT_HD_ID.PROJECT_STRATEGIC_PRIORITY

Project

General - (Project)

Project Risk Exposure

Dimension

The calculated exposure value for the risk

Value Derived From : Dim_W_PROJECT_HD_ID.PROJECT_RISK_EXPOSURE

Project

General - (Project)

Project Risk Level

Dimension

Project risk level (1 - Very Low, 2 - Low, 3 - Medium, 4 - High, 5 - Very High)

Value Derived From : Dim_W_PROJECT_HD_ID.PROJECT_RISK_LEVEL

Project

General - (Project)

Project Risk Score

Dimension

The calculated score value of the impact values assigned to the risk

Value Derived From : Dim_W_PROJECT_HD_ID.PROJECT_RISK_SCORE

Project

General - (Project)

WBS

Dimension

The Unique ID of the project's root level WBS

Value Derived From : Dim_W_PROJECT_HD_ID.WBS_OBJECT_ID

Project

General - (Project)

Project Status

Dimension

The status of the project as active, inactive, planned or what-if

Value Derived From : Dim_W_PROJECT_HD_ID.PROJECT_STATUS

Project

General - (Project)

Strategic Priority

Dimension

Range 1 to 10,000

Value Derived From : Dim_W_PROJECT_HD_ID.PROJECT_STRATEGIC_PRIORITY

Project

Location - (Project)

Location - (Project)

 

Project Location

 

Project

Location - (Project)

Address Line 1

Dimension

The first line of the address

Value Derived From : Dim_W_PROJECT_HD_ID.ADDRESS_LINE1

Project

Location - (Project)

Address Line 2

Dimension

The second line of the address

Value Derived From : Dim_W_PROJECT_HD_ID.ADDRESS_LINE2

Project

Location - (Project)

City Name

Dimension

The city name for this Location

Value Derived From : Dim_W_PROJECT_HD_ID.CITY_NAME

Project

Location - (Project)

Country Code

Dimension

The country code for this Location

Value Derived From : Dim_W_PROJECT_HD_ID.COUNTRY_CODE

Project

Location - (Project)

Country Name

Dimension

The country name for this Location

Value Derived From : Dim_W_PROJECT_HD_ID.COUNTRY_NAME

Project

Location - (Project)

Latitude

Dimension

The latitude for this Location

Value Derived From : Dim_W_PROJECT_HD_ID.LATITUDE

Project

Location - (Project)

Location Name

Dimension

The name of the location

Value Derived From : Dim_W_PROJECT_HD_ID.LOCATION_NAME

Project

Location - (Project)

Location Type

Dimension

Location Type

Value Derived From : Dim_W_PROJECT_HD_ID.LOCATION_TYPE

Project

Location - (Project)

Longitude

Dimension

The longitude for this Location

Value Derived From : Dim_W_PROJECT_HD_ID.LONGITUDE

Project

Location - (Project)

Municipality Name

Dimension

The municipality name for this Location

Value Derived From : Dim_W_PROJECT_HD_ID.MUNICIPALITY_NAME

Project

Location - (Project)

Postal Code

Dimension

The postal code for this Location

Value Derived From : Dim_W_PROJECT_HD_ID.POSTAL_CODE

Project

Location - (Project)

State/Province Code

Dimension

The state abbreviation for this Location

Value Derived From : Dim_W_PROJECT_HD_ID.STATE_CODE

Project

Location - (Project)

State/Province Name

Dimension

The state name for this Location

Value Derived From : Dim_W_PROJECT_HD_ID.STATE_NAME

Project

P6 Links

 

 

Go to P6 Links

 

Project

P6 Links

Link to Activities

Dimension

Go to Project Activities

'<a target="_blank" href="' || VALUEOF(NQ_SESSION."DW_P6_LINK_BASE_URL") || VALUEOF("DW_P6_LINK_PROJECT_LIST_BASE_URL") || CAST (P6Core."Dim - Project HD ID"."Project WBS Object Id" AS VARCHAR ( 10 )) || '%26key%3Dactivities">' || 'Project Activities' || '</a>'

Project

P6 Links

Link to Documents

Dimension

Go to Project Documents

'<a target="_blank" href="' || VALUEOF(NQ_SESSION."DW_P6_LINK_BASE_URL") || VALUEOF("DW_P6_LINK_PROJECT_LIST_BASE_URL") || CAST (P6Core."Dim - Project HD ID"."Project WBS Object Id" AS VARCHAR ( 10 )) || '%26key%3Ddocuments">' || 'Project Documents' || '</a>'

Project

P6 Links

Link to Issues

Dimension

Go to Project Issues

'<a target="_blank" href="' || VALUEOF(NQ_SESSION."DW_P6_LINK_BASE_URL") || '/action/pm/lwfissuemanagement?projectId=' || CAST (P6Core."Dim - Project HD ID"."Project Object Id" AS VARCHAR ( 10 )) || '&wbsId=' || CAST (P6Core."Dim - Project HD ID"."Project WBS Object Id" AS VARCHAR ( 10 )) || '&checkTabs=true">' || 'Project Issues' || '</a>'

Project

P6 Links

Link to Risks

Dimension

Go to Project Risks

'<a target="_blank" href="' || VALUEOF(NQ_SESSION."DW_P6_LINK_BASE_URL") || VALUEOF("DW_P6_LINK_PROJECT_LIST_BASE_URL") || CAST (P6Core."Dim - Project HD ID"."Project WBS Object Id" AS VARCHAR ( 10 )) || '%26key%3Drisks">' || 'Project Risks' || '</a>'

Project

P6 Links

Link to Team Usage

Dimension

Go to Project Team Usage

'<a target="_blank" href="' || VALUEOF(NQ_SESSION."DW_P6_LINK_BASE_URL") || VALUEOF("DW_P6_LINK_PROJECT_LIST_BASE_URL") || CAST (P6Core."Dim - Project HD ID"."Project WBS Object Id" AS VARCHAR ( 10 )) || '%26key%3Dteamusage">' || 'Project Team Usage' || '</a>'

Project

Notebooks - (Project)

 

 

Project level notebook topics.

 

Project

Notebooks - (Project)

Create Date

Dimension

The date the notebook topic was created

Value Derived From : Dim_W_PROJECT_NOTE_D_ID.W_CREATE_DT

Project

Notebooks - (Project)

Create User

Dimension

The user that created the notebook topic

Value Derived From : Dim_W_PROJECT_NOTE_D_ID.W_CREATE_USER

Project

Notebooks - (Project)

Notebook Text

Lookup

The text of the notebook topic

Lookup(DENSE "P6Core"."Lookup - Project Note D ID"."Raw Text", "P6Core"."Dim - Project Note D ID"."Note Key", "P6Core"."Dim - Project Note D ID"."Project Key")

Project

Notebooks - (Project)

Notebook Topic Name

Dimension

The name of the notebook topic

Value Derived From : Dim_W_PROJECT_NOTE_D_ID.NOTEBOOK_TOPIC_NAME

Project

Notebooks - (Project)

Update Date

Dimension

The date the notebook topic was updated

Value Derived From : Dim_W_PROJECT_NOTE_D_ID.W_UPDATE_DT

Project

Notebooks - (Project)

Update User

Dimension

The last user to update notebook topic

Value Derived From : Dim_W_PROJECT_NOTE_D_ID.W_UPDATE_USER

 

 

 

 

 

 

Fact - Primavera - Burn Down Folder

 

 

 

 

 

Fact - Primavera - Burn Down

Costs

Actual Cost

Fact

The actual non-overtime plus overtime cost for the resource assignment on the activity. Calculated as Actual Regular Cost plus Actual Overtime Cost.

Value Derived From : Fact_W_ACTIVITY_WORK_DOWN_HF_WDAct.ACTUAL_COST

Fact - Primavera - Burn Down

Costs

Actual Cost Burn

Fact

The actual cost distributed over the activity duration

Value Derived From : Fact_W_ACTIVITY_WORK_DOWN_HF_WDAct.ACTUAL_COST_BURN

Fact - Primavera - Burn Down

Costs

Baseline Cost

Fact

Planned Cost from the Burn Down snapshot

Value Derived From : Fact_W_ACTIVITY_WORK_DOWN_HF_WDAct.BASELINE_COST

Fact - Primavera - Burn Down

Costs

Baseline Cost Burn

Fact

The expected remaining cost distributed over the activity duration based on Burn Down snapshot

Value Derived From : Fact_W_ACTIVITY_WORK_DOWN_HF_WDAct.BASELINE_COST_BURN

Fact - Primavera - Burn Down

Costs

At Completion Cost

Fact

The sum of the Actual Costs plus Remaining Costs

Value Derived From : Fact_W_ACTIVITY_WORK_DOWN_HF_WDAct.COMPLETE_COST

Fact - Primavera - Burn Down

Costs

Remaining Cost

Fact

The remaining cost for the resource assignment on the activity. Calculated as Remaining Units multiplied by Cost/Time.

Value Derived From : Fact_W_ACTIVITY_WORK_DOWN_HF_WDAct.REMAINING_COST

Fact - Primavera - Burn Down

Costs

Remaining Cost Burn

Fact

The remaining cost distributed over the activity duration

Value Derived From : Fact_W_ACTIVITY_WORK_DOWN_HF_WDAct.REMAINING_COST_BURN

 

 

 

 

 

 

Activity Folder

 

 

 

 

 

Activity

Dates - (Activity)

 

 

Activity Dates

 

Activity

Dates - (Activity)

Actual Finish

Dimension

The date on which the activity actually finished

Value Derived From : Dim_W_ACTIVITY_D_Activity.ACTUAL_FINISH_DATE

Activity

Dates - (Activity)

Actual Start

Dimension

The date on which the activity actually started

Value Derived From : Dim_W_ACTIVITY_D_Activity.ACTUAL_START_DATE

Activity

Dates - (Activity)

Baseline Project Finish

Dimension

The Project Baseline Planned Finish Date.

Value Derived From : Dim_W_ACTIVITY_D_Activity.BASELINE_FINISH_DATE

Activity

Dates - (Activity)

Baseline Project Start

Dimension

The Project Baseline Planned Start Date.

Value Derived From : Dim_W_ACTIVITY_D_Activity.BASELINE_START_DATE

Activity

Dates - (Activity)

Data Date

Dimension

The current data date for the project. The project status is up to date as of the data date. The data date is modified when project actuals are applied.

Value Derived From : Dim_W_ACTIVITY_D_Activity.DATA_DATE

Activity

Dates - (Activity)

Early Finish

Dimension

The earliest possible date the activity can finish. This date is calculated by the project scheduler based on activity relationships, schedule constraints, and resource availability.

Value Derived From : Dim_W_ACTIVITY_D_Activity.EARLY_FINISH_DATE

Activity

Dates - (Activity)

Early Start

Dimension

The earliest possible date the remaining work for the activity can begin. This date is calculated by the project scheduler based on activity relationships, schedule constraints, and resource availability.

Value Derived From : Dim_W_ACTIVITY_D_Activity.EARLY_START_DATE

Activity

Dates - (Activity)

Expected Finish

Dimension

The date the activity is expected to finish. Typically, this date is entered in the Timesheets module by the primary resource.

Value Derived From : Dim_W_ACTIVITY_D_Activity.EXPECT_FINISH_DATE

Activity

Dates - (Activity)

External Early Start

Dimension

The External Early Start date is the earliest finish date of all lost external relationships. This field is populated only during import when a relationship is lost because it does not exist in the current database. This date may be used to calculate the start date of the current activity in place of the true relationship when scheduling.

Value Derived From : Dim_W_ACTIVITY_D_Activity.EXTERNAL_EARLY_START_DATE

Activity

Dates - (Activity)

External Late Finish

Dimension

The External Late Finish date is the latest start date of all lost external relationships. This field is populated only during import when a relationship is lost because it does not exist in the current database. This date may be used to calculate the finish date of the current activity in place of the true relationship when scheduling.

Value Derived From : Dim_W_ACTIVITY_D_Activity.EXTERNAL_LATE_FINISH_DATE

Activity

Dates - (Activity)

Finish

Dimension

The current finish date of the activity. Set to the activity remaining early finish date while the activity is not started or in progress, and the actual finish date once the activity is completed.

Value Derived From : Dim_W_ACTIVITY_D_Activity.FINISH_DATE

Activity

Dates - (Activity)

Late Finish

Dimension

The latest possible date the activity must finish without delaying the project finish date. This date is calculated by the project scheduler based on activity relationships, schedule constraints, and resource availability.

Value Derived From : Dim_W_ACTIVITY_D_Activity.LATE_FINISH_DATE

Activity

Dates - (Activity)

Late Start

Dimension

The latest possible date the remaining work for the activity must begin without delaying the project finish date. This date is calculated by the project scheduler based on activity relationships, schedule constraints, and resource availability.

Value Derived From : Dim_W_ACTIVITY_D_Activity.LATE_START_DATE

Activity

Dates - (Activity)

Planned Finish

Dimension

The date the activity is scheduled to finish. This date is computed by the project scheduler but can be updated manually by the project manager. This date is not changed by the project scheduler after the activity has been started.

Value Derived From : Dim_W_ACTIVITY_D_Activity.PLANNED_FINISH_DATE

Activity

Dates - (Activity)

Planned Start

Dimension

The date the activity is scheduled to begin. This date is computed by the project scheduler but can be updated manually by the project manager. This date is not changed by the project scheduler after the activity has been started.

Value Derived From : Dim_W_ACTIVITY_D_Activity.PLANNED_START_DATE

Activity

Dates - (Activity)

Primary Constraint Date

Dimension

The constraint date for the activity, if the activity has a constraint. The activity's constraint type determines whether this is a start date or finish date. Activity constraints are used by the project scheduler.

Value Derived From : Dim_W_ACTIVITY_D_Activity.PRIMARY_CONSTRAINT_DATE

Activity

Dates - (Activity)

Remaining Early Finish

Dimension

The date the remaining work for the activity is scheduled to finish. This date is computed by the project scheduler but can be updated manually by the project manager. Before the activity is started, the remaining finish date is the same as the planned finish date. This is the finish date that Progress Reporter users follow.

Value Derived From : Dim_W_ACTIVITY_D_Activity.REMAINING_FINISH_DATE

Activity

Dates - (Activity)

Remaining Early Start

Dimension

The date the remaining work for the activity is scheduled to begin. This date is computed by the project scheduler but can be updated manually by the project manager. Before the activity is started, the remaining start date is the same as the planned start date. This is the start date that Progress Reporter users follow.

Value Derived From : Dim_W_ACTIVITY_D_Activity.REMAINING_START_DATE

Activity

Dates - (Activity)

Remaining Late Finish

Dimension

Remaining late end date is calculated by the scheduler.

Value Derived From : Dim_W_ACTIVITY_D_Activity.REMAINING_LATE_FINISH_DATE

Activity

Dates - (Activity)

Remaining Late Start

Dimension

Remaining late start date is calculated by the scheduler.

Value Derived From : Dim_W_ACTIVITY_D_Activity.REMAINING_LATE_START_DATE

Activity

Dates - (Activity)

Resume Date

Dimension

The date progress is resumed on an activity.

Value Derived From : Dim_W_ACTIVITY_D_Activity.RESUME_DATE

Activity

Dates - (Activity)

Secondary Constraint Date

Dimension

The second constraint date for the activity, if the activity has a constraint.

Value Derived From : Dim_W_ACTIVITY_D_Activity.SECONDARY_CONSTRAINT_DATE

Activity

Dates - (Activity)

Start

Dimension

The current start date of the activity. Set to the activity remaining early start date while the activity is not started, and the actual start date once the activity is started.

Value Derived From : Dim_W_ACTIVITY_D_Activity.START_DATE

Activity

Dates - (Activity)

Suspend Date

Dimension

The date progress is suspended on an activity.

Value Derived From : Dim_W_ACTIVITY_D_Activity.SUSPEND_DATE

Activity

Durations - (Activity)

 

 

Activity Durations

 

Activity

Durations - (Activity)

Actual Duration

Dimension

Actual duration is the total working time from the activity actual start date to the actual finish date (for completed activities), or to the current data date (for in-progress activities). The actual working time is computed using the activity's calendar.

Value Derived From : Dim_W_ACTIVITY_D_Activity.ACTUAL_DURATION

Activity

Durations - (Activity)

At Completion Duration

Dimension

The duration at completion is the total working time from the activity's current start date to the current finish date. The current start date is the planned start date until the activity is started, then it is the actual start date. The current finish date is the activity planned finish date while the activity is not started, the remaining finish date while the activity is in progress, and the actual finish date once the activity is completed. The total working time is computed using the activity's calendar.

Value Derived From : Dim_W_ACTIVITY_D_Activity.AT_COMPLETION_DURATION

Activity

Durations - (Activity)

Baseline Project Duration

Dimension

The duration for the activity in the primary baseline.

Value Derived From : Dim_W_ACTIVITY_D_Activity.BASELINE_DURATION

Activity

Durations - (Activity)

Baseline Planned Duration

Dimension

Baseline Planned Duration is the total working time from the baseline activity planned start date to the baseline planned finish date. The baseline planned working time is computed using the activity's calendar.

Value Derived From : Dim_W_ACTIVITY_D_Activity.BASELINE_PLANNED_DURATION

Activity

Durations - (Activity)

Free Float

Dimension

The amount of time the activity can be delayed before delaying the start date of any successor activity.

Value Derived From : Dim_W_ACTIVITY_D_Activity.FREE_FLOAT

Activity

Durations - (Activity)

Original Duration

Dimension

Original Duration is the total working time from the activity planned start date to the planned finish date. The planned working time is computed using the activity's calendar.

Value Derived From : Dim_W_ACTIVITY_D_Activity.PLANNED_DURATION

Activity

Durations - (Activity)

Remaining Duration

Dimension

Remaining duration is the total working time from the activity remaining start date to the remaining finish date. The remaining working time is computed using the activity's calendar. Before the activity is started, the remaining duration is the same as the Original Duration. After the activity is completed the remaining duration is zero.

Value Derived From : Dim_W_ACTIVITY_D_Activity.REMAINING_DURATION

Activity

Durations - (Activity)

Remaining Float

Dimension

The amount of time remaining by which the activity can be delayed before delaying the project finish date. Computed as Late Finish - Remaining Finish. If the remaining finish is the same as the early finish ( in general, when the activity is not started), then the remaining float is the same as the total float.

Value Derived From : Dim_W_ACTIVITY_D_Activity.REMAINING_FLOAT

Activity

Durations - (Activity)

Total Float

Dimension

The amount of time the activity can be delayed before delaying the project finish date. Total float can be computed as Late Start - Early Start or as Late Finish - Early Finish; this option can be set when running the project scheduler.

Value Derived From : Dim_W_ACTIVITY_D_Activity.TOTAL_FLOAT

Activity

Durations - (Activity)

Variance - Baseline Project Duration

Dimension

Variance duration is the duration between the activity' Baseline project duration and the At Completion duration.

Value Derived From : Dim_W_ACTIVITY_D_Activity.DURATION_VARIANCE

Activity

Durations - (Activity)

Variance - Baseline Project Finish Date

Dimension

Variance Finish Date is the duration between the Baseline project finish date and the finish date in the current project.

Value Derived From : Dim_W_ACTIVITY_D_Activity.FINISH_DATE_VARIANCE

Activity

Durations - (Activity)

Variance - Baseline Project Start Date

Dimension

Variance Start Date is the duration between the Baseline project start date and the start date in the current project.

Value Derived From : Dim_W_ACTIVITY_D_Activity.START_DATE_VARIANCE

Activity

General - (Activity)

 

 

General Activity Information

 

Activity

General - (Activity)

Activity ID

Dimension

A short ID which uniquely identifies the activity within the project.

Value Derived From : Dim_W_ACTIVITY_HD_ID.ACTIVITY_ID

Activity

General - (Activity)

Activity Name

Dimension

The name of the activity. The activity name does not have to be unique.

Value Derived From : Dim_W_ACTIVITY_HD_ID.ACTIVITY_NAME

Activity

General - (Activity)

Owner

Dimension

User who owns the activity.

Value Derived From : Dim_W_ACTIVITY_HD_ID.ACTIVITY_OWNER

Activity

General - (Activity)

Activity Status

Dimension

The current status of the activity, either Not Started, In Progress, or Completed.

Value Derived From : Dim_W_ACTIVITY_HD_ID.ACTIVITY_STATUS

Activity

General - (Activity)

Activity Type

Dimension

The type of activity, either 'Task Dependent', 'Resource Dependent', 'Level of Effort', 'Start Milestone' or 'Finish Milestone'. A Task Dependent activity is scheduled using the activity's calendar rather than the calendars of the assigned resources. A Resource Dependent activity is scheduled using the calendars of the assigned resources. This type is used when several resources are assigned to the activity, but they may work separately. A Start/Finish Milestone is a zero-duration activity, marking a significant start/end of project event. A Level of Effort activity has a duration which is determined by its dependent activities. Administration-type activities are typically level of effort.

Value Derived From : Dim_W_ACTIVITY_HD_ID.ACTIVITY_TYPE

Activity

General - (Activity)

Auto Compute Actuals

Dimension

Identifies whether the actual and remaining units, start date, finish date, and percent complete for the activity are computed automatically using the planned dates, budgeted units and the activity's schedule percent complete. If this option is selected, the actual/remaining units and actual dates are automatically updated when project actuals are applied. This assumes that all work for the activity proceeds according to plan.

Value Derived From : Dim_W_ACTIVITY_HD_ID.AUTO_COMPUTE_ACTUALS_FLAG

Activity

General - (Activity)

Calendar Name

Dimension

The calendar assigned to the activity. Activity calendars can be assigned from the global calendar pool or the project calendar pool.

Value Derived From : Dim_W_ACTIVITY_HD_ID.CALENDAR_NAME

Activity

General - (Activity)

Criticality Index

Dimension

Criticality Index

Value Derived From : Dim_W_ACTIVITY_HD_ID.CRITICALITY_INDEX

Activity

General - (Activity)

Duration Type

Dimension

The duration type of the activity. One of Fixed Units per Time, Fixed Duration, or Fixed Units. For Fixed Units per Time activities, the resource units per time are constant when the activity duration or units are changed. This type is used when an activity has fixed resources with fixed productivity output per time period. For Fixed Duration activities, the activity duration is constant as the units or resource units per time are changed. This type is used when the activity is to be completed within a fixed time period regardless of the resources assigned. For Fixed Units activities, the activity units are constant when the duration or resource units per time are changed. This type is used when the total amount of work is fixed, and increasing the resources can decrease the activity duration.

Value Derived From : Dim_W_ACTIVITY_HD_ID.DURATION_TYPE

Activity

General - (Activity)

Critical

Dimension

Indicates whether the activity is critical. An activity is critical when its Total Float is below the critical duration specified for the project. Delaying critical activities will delay the finish date of the project.

Value Derived From : Dim_W_ACTIVITY_HD_ID.IS_CRITICAL

Activity

General - (Activity)

Longest Path

Dimension

Indicates whether an activity is on the longest path. The longest path is defined as activities that are on the critical path and determine the end date of the project. Defining critical activities based on the longest path in the project provides an alternative to viewing critical activities based on float.

Value Derived From : Dim_W_ACTIVITY_HD_ID.IS_LONGEST_PATH

Activity

General - (Activity)

Activity Leveling Priority

Dimension

The activity priority can be used to prioritize activities in a project when performing resource leveling.

Value Derived From : Dim_W_ACTIVITY_HD_ID.LEVELING_PRIORITY

Activity

General - (Activity)

Percent Complete Type

Dimension

The activity percent complete type is one of Duration, Units, or Physical. The percent complete type controls whether the Activity % Complete is tied to the Duration % Complete, the Units % Complete, or the Physical % Complete for the activity. Set the percent complete type to Duration for activities which are duration driven, for example, administration tasks and training classes. Set the percent complete type to Physical for activities which are work-product driven, for example, creating a document or a product. Set the percent complete type to Units for activities which are work effort driven, for example, providing a consulting service.

Value Derived From : Dim_W_ACTIVITY_HD_ID.COMPLETE_PCT_TYPE

Activity

General - (Activity)

Primary Constraint

Dimension

The type of constraint applied to the activity start or finish date. Activity constraints are used by the project scheduler. Start date constraints are 'Start On', 'Start On or Before', 'Start On or After' and 'Mandatory Start'. Finish date constraints are 'Finish On', 'Finish On or Before', 'Finish On or After' and 'Mandatory Finish'. Another type of constraint, 'As Late as Possible', schedules the activity as late as possible based on the available free float.

Value Derived From : Dim_W_ACTIVITY_HD_ID.PRIMARY_CONSTRAINT_TYPE

Activity

General - (Activity)

Primary Resource

Dimension

The primary resource for the activity. The primary resource is responsible for the overall work on the activity and updates the activity status using Progress Reporter.

Value Derived From : Dim_W_ACTIVITY_HD_ID.PRIMARY_RESOURCE_NAME

Activity

General - (Activity)

Secondary Constraint

Dimension

The second type of constraint applied to the activity start or finish date.

Value Derived From : Dim_W_ACTIVITY_HD_ID.SECONDARY_CONSTRAINT_TYPE

Activity

General - (Activity)

WBS Code

Dimension

The WBS for the activity.

Value Derived From : Dim_W_ACTIVITY_HD_ID.WBS_CODE

Activity

General - (Activity)

WBS Name

Dimension

The Work Breakdown Structure Name.

Value Derived From : Dim_W_ACTIVITY_HD_ID.WBS_NAME

Activity

Location - (Activity)

 

 

Activity Location

 

Activity

Location - (Activity)

Address Line 1

Dimension

The first line of the address

Value Derived From : Dim_W_ACTIVITY_HD_ID.ADDRESS_LINE1

Activity

Location - (Activity)

Address Line 2

Dimension

The second line of the address

Value Derived From : Dim_W_ACTIVITY_HD_ID.ADDRESS_LINE2

Activity

Location - (Activity)

City Name

Dimension

The city name for this Location

Value Derived From : Dim_W_ACTIVITY_HD_ID.CITY_NAME

Activity

Location - (Activity)

Country Code

Dimension

The country code for this Location

Value Derived From : Dim_W_ACTIVITY_HD_ID.COUNTRY_CODE

Activity

Location - (Activity)

Country Name

Dimension

The country name for this Location

Value Derived From : Dim_W_ACTIVITY_HD_ID.COUNTRY_NAME

Activity

Location - (Activity)

Latitude

Dimension

The latitude for this Location

Value Derived From : Dim_W_ACTIVITY_HD_ID.LATITUDE

Activity

Location - (Activity)

Location Name

Dimension

The name of the location

Value Derived From : Dim_W_ACTIVITY_HD_ID.LOCATION_NAME

Activity

Location - (Activity)

Location Type

Dimension

Location Type

Value Derived From : Dim_W_ACTIVITY_HD_ID.LOCATION_TYPE

Activity

Location - (Activity)

Longitude

Dimension

The longitude for this Location

Value Derived From : Dim_W_ACTIVITY_HD_ID.LONGITUDE

Activity

Location - (Activity)

Municipality Name

Dimension

The municipality name for this Location

Value Derived From : Dim_W_ACTIVITY_HD_ID.MUNICIPALITY_NAME

Activity

Location - (Activity)

Postal Code

Dimension

The postal code for this Location

Value Derived From : Dim_W_ACTIVITY_HD_ID.POSTAL_CODE

Activity

Location - (Activity)

State/Province Code

Dimension

The state abbreviation for this Location

Value Derived From : Dim_W_ACTIVITY_HD_ID.STATE_CODE

Activity

Location - (Activity)

State/Province Name

Dimension

The state name for this Location

Value Derived From : Dim_W_ACTIVITY_HD_ID.STATE_NAME

Activity

Multiple Float Paths - (Activity)

 

 

Activity Multiple Float Paths

 

Activity

Multiple Float Paths - (Activity)

Float Path

Dimension

The project scheduler determines the most critical and sub-critical paths. The float path field identifies the critical path that each activity is on. The number starts from 1 (where 1 is most critical) to the max number of float paths identified by the scheduler. This field is used when determining multiple float paths using the Free Float and Total Float method.

Value Derived From : Dim_W_ACTIVITY_HD_ID.FLOAT_PATH

Activity

Multiple Float Paths - (Activity)

Float Path Order

Dimension

This field is computed by the project scheduler and identifies the order in which the activities were processed within the float path.

Value Derived From : Dim_W_ACTIVITY_HD_ID.FLOAT_PATH_ORDER

Activity

Percent Completes - (Activity)

 

 

Activity Percent Completes

 

Activity

Percent Completes - (Activity)

Duration % Of Planned

Dimension

The percent complete of the activity duration. Computed as (Planned Duration - Remaining Duration)/Original Duration * 100. Always in the range 0 to 100. The Planned Duration is taken from the current plan, not from the baseline.

Value Derived From : Dim_W_ACTIVITY_HD_ID.DURATION_PCT_OF_PLANNED

Activity

Percent Completes - (Activity)

Duration % Complete

Dimension

The percent complete of the activity duration. Computed as (Original Duration - Remaining Duration)/Original Duration * 100. Always in the range 0 to 100. The Original Duration is taken from the current plan, not from the baseline.

Value Derived From : Dim_W_ACTIVITY_HD_ID.DURATION_PCT_COMPLETE

Activity

Percent Completes - (Activity)

Expense Cost % Complete

Dimension

Percent complete of cost for all expenses associated with an activity. Computed as Actual Expense Cost / At Completion Expense Cost* 100. Always in the range 0 to 100.

Value Derived From : Dim_W_ACTIVITY_HD_ID.EXPENSE_COST_PCT_COMPLETE

Activity

Percent Completes - (Activity)

Labor Units % Complete

Dimension

The percent complete of units for all labor resources for the activity. Computed as Actual Labor Units / At Completion Labor Units * 100. Always in the range 0 to 100.

Value Derived From : Dim_W_ACTIVITY_HD_ID.LABOR_UNITS_PCT_COMPLETE

Activity

Percent Completes - (Activity)

Nonlabor Cost % Complete

Dimension

The percent complete of cost for all nonlabor resources assigned to the activity. Computed as Actual Nonlabor Cost / At Completion Nonlabor Cost * 100. Always in the range 0 to 100.

Value Derived From : Dim_W_ACTIVITY_HD_ID.NONLABOR_COST_PCT_COMPLETE

Activity

Percent Completes - (Activity)

Nonlabor Units % Complete

Dimension

The percent complete of units for all nonlabor resources for the activity. Computed as Actual Nonlabor Units / At Completion Nonlabor Units * 100. Always in the range 0 to 100.

Value Derived From : Dim_W_ACTIVITY_HD_ID.NONLABOR_UNITS_PCT_COMPLETE

Activity

Percent Completes - (Activity)

Percent Complete

Dimension

The activity percent complete. This value is tied to the activity Duration % Complete, Units % Complete, or Physical % Complete, depending on the setting for the activity's Percent Complete Type, which is one of Duration, Units, or Physical. Always in the range 0 to 100.

Value Derived From : Dim_W_ACTIVITY_HD_ID.PERCENT_COMPLETE

Activity

Percent Completes - (Activity)

Performance % Complete

Dimension

The activity performance percent complete. The performance percent complete is used to compute earned value and may be based on the Activity % Complete, on the 0/100 rule, on the 50/50 rule, etc., depending on the technique for computing earned-value percent complete for the activity's WBS. The Performance % Complete specifies what percentage of the activity's planned worth has been earned so far.

Value Derived From : Dim_W_ACTIVITY_HD_ID.PERFORMANCE_PCT_COMPLETE

Activity

Percent Completes - (Activity)

Physical % Complete

Dimension

The physical percent complete can either be user entered or calculated from the activity's weighted steps. There is a project setting specifying this.

Value Derived From : Dim_W_ACTIVITY_HD_ID.PHYSICAL_PCT_COMPLETE

Activity

Percent Completes - (Activity)

Schedule % Complete

Dimension

The activity schedule percent complete. The Schedule % Complete specifies how much of the activity's baseline duration has been completed so far. Computed based on where the current data date falls between the activity's baseline start and finish dates. If the data date is earlier than the baseline Start, the Schedule % Complete is 0. If the data date is later than the baseline Finish, the Schedule % Complete is 100. The Schedule % Complete indicates how much of the activity duration should be currently completed, relative to the selected baseline.

Value Derived From : Dim_W_ACTIVITY_HD_ID.SCHEDULE_PCT_COMPLETE

Activity

Percent Completes - (Activity)

Units % Complete

Dimension

The percent complete of units for all labor and nonlabor resources assigned to the activity. Computed as Actual Units / At Completion Units * 100. Always in the range 0 to 100.

Value Derived From : Dim_W_ACTIVITY_HD_ID.UNITS_PCT_COMPLETE

Activity

Notebooks - (Activity)

 

 

Activity level notebook topics.

 

Activity

Notebooks - (Activity)

Create Date

Dimension

The date the notebook topic was created

Value Derived From : Dim_W_ACTIVITY_NOTE_D_Activity_Note.W_CREATE_DT

Activity

Notebooks - (Activity)

Create User

Dimension

The user that created the notebook topic

Value Derived From : Dim_W_ACTIVITY_NOTE_D_Activity_Note.W_CREATE_USER

Activity

Notebooks - (Activity)

Notebook Text

 

The text of the notebook topic

Value Derived From : LOOKUP(DENSE "P6Core"."Lookup - Activity Note"."Raw Text", "P6Core"."Dim - Activity Note"."Note Key", "P6Core"."Dim - Activity Note"."Activity Key")

Activity

Notebooks - (Activity)

Notebook Topic Name

Dimension

The name of the notebook topic

Value Derived From : Dim_W_ACTIVITY_NOTE_D_Activity_Note.NOTEBOOK_TOPIC_NAME

Activity

Notebooks - (Activity)

Update Date

Dimension

The date the notebook topic was updated

Value Derived From : Dim_W_ACTIVITY_NOTE_D_Activity_Note.W_UPDATE_DT

Activity

Notebooks - (Activity)

Update User

Dimension

The last user to update notebook topic

Value Derived From : Dim_W_ACTIVITY_NOTE_D_Activity_Note.W_UPDATE_USER

 

 

 

 

 

 

Resource Assignment Folder

 

 

 

 

 

Resource Assignment

Dates - (Resource Assignment)

 

 

 

 

Resource Assignment

Dates - (Resource Assignment)

Actual Finish

Dimension

The date on which the assignment is complete.

Value Derived From : Dim_W_ASSIGNMENT_HD_ID.ACTUAL_FINISH_DATE

Resource Assignment

Dates - (Resource Assignment)

Actual Start

Dimension

The date on which the assignment actually started.

Value Derived From : Dim_W_ASSIGNMENT_HD_ID.ACTUAL_START_DATE

Resource Assignment

Dates - (Resource Assignment)

Planned Finish

Dimension

The date the assignment is scheduled to be finished.

Value Derived From : Dim_W_ASSIGNMENT_HD_ID.PLANNED_FINISH_DATE

Resource Assignment

Dates - (Resource Assignment)

Planned Start

Dimension

The date work on the assignment is scheduled to begin.

Value Derived From : Dim_W_ASSIGNMENT_HD_ID.PLANNED_START_DATE

Resource Assignment

Dates - (Resource Assignment)

Remaining Finish

Dimension

The date the assignment is scheduled to be finished. This date can be updated manually by the user. Before the activity is started, this date is the same as the Planned Finish date.

Value Derived From : Dim_W_ASSIGNMENT_HD_ID.REMAINING_FINISH_DATE

Resource Assignment

Dates - (Resource Assignment)

Remaining Start

Dimension

The date the assignment is scheduled to begin. This date can be updated manually by the user. Before the activity is started, this date is the same as the Planned Start date.

Value Derived From : Dim_W_ASSIGNMENT_HD_ID.REMAINING_START_DATE

Resource Assignment

General - (Resource Assignment)

Resource Name

Dimension

The name of the resource for this assignment

Value Derived From : Dim_W_ASSIGNMENT_HD_ID.RESOURCE_NAME

Resource Assignment

General - (Resource Assignment)

Role Name

Dimension

The name of the role for this assignment

Value Derived From : Dim_W_ASSIGNMENT_HD_ID.ROLE_NAME

 

 

 

 

 

 

Resource Folder

 

 

 

 

 

Resource

General - (Resource)

 

 

General Resource Information

 

Resource

General - (Resource)

Active

Dimension

Indicates whether the resource is currently active. Nonactive resources may have left the organization but are not deleted from the system since they may have actual hours.

Value Derived From : Dim_W_RESOURCE_HD_ID.ACTIVE_FLAG

Resource

General - (Resource)

Datasource Id

Dimension

A unique source Id created for the Primavera data source being used. Used to identify data sources when using multiple Primavera data sources.

Value Derived From : Dim_W_RESOURCE_HD_ID.DATASOURCE_ID

Resource

General - (Resource)

Primary Role Name

Dimension

The name of the role that is assigned as the resource's primary role.

Value Derived From : Dim_W_RESOURCE_HD_ID.PRIMARY_ROLE_NAME

Resource

General - (Resource)

Unique Primary Role Id

Dimension

The unique Id of the role that is assigned as the resource's primary role.

Value Derived From : Dim_W_RESOURCE_HD_ID.PRIMARY_ROLE_OBJECT_ID

Resource

General - (Resource)

Resource ID

Dimension

A short code which uniquely identifies the resource.

Value Derived From : Dim_W_RESOURCE_HD_ID.RESOURCE_ID

Resource

General - (Resource)

Resource Name

Dimension

The name of the resource

Value Derived From : Dim_W_RESOURCE_HD_ID.RESOURCE_NAME

Resource

General - (Resource)

Title

Dimension

The title of the resource

Value Derived From : Dim_W_RESOURCE_HD_ID.RESOURCE_TITLE

Resource

General - (Resource)

Resource Type

Dimension

Indicates whether the resource is labor, nonlabor, or material.

Value Derived From : Dim_W_RESOURCE_HD_ID.RESOURCE_TYPE

Resource

Codes - (Resource)

 

 

Resource Codes

Resource

Location - (Resource)

 

 

Resource Location

 

Resource

Location - (Resource)

Address Line 1

Dimension

The first line of the address

Value Derived From : Dim_W_RESOURCE_HD_ID.ADDRESS_LINE1

Resource

Location - (Resource)

Address Line 2

Dimension

The second line of the address

Value Derived From : Dim_W_RESOURCE_HD_ID.ADDRESS_LINE2

Resource

Location - (Resource)

City Name

Dimension

The city name for this Location

Value Derived From : Dim_W_RESOURCE_HD_ID.CITY_NAME

Resource

Location - (Resource)

Country Code

Dimension

The country code for this Location

Value Derived From : Dim_W_RESOURCE_HD_ID.COUNTRY_CODE

Resource

Location - (Resource)

Country Name

Dimension

The country name for this Location

Value Derived From : Dim_W_RESOURCE_HD_ID.COUNTRY_NAME

Resource

Location - (Resource)

Latitude

Dimension

The latitude for this Location

Value Derived From : Dim_W_RESOURCE_HD_ID.LATITUDE

Resource

Location - (Resource)

Location Name

Dimension

The name of the location

Value Derived From : Dim_W_RESOURCE_HD_ID.LOCATION_NAME

Resource

Location - (Resource)

Location Type

Dimension

Location Type

Value Derived From : Dim_W_RESOURCE_HD_ID.LOCATION_TYPE

Resource

Location - (Resource)

Longitude

Dimension

The longitude for this Location

Value Derived From : Dim_W_RESOURCE_HD_ID.LONGITUDE

Resource

Location - (Resource)

Municipality Name

Dimension

The municipality name for this Location

Value Derived From : Dim_W_RESOURCE_HD_ID.MUNICIPALITY_NAME

Resource

Location - (Resource)

Postal Code

Dimension

The postal code for this Location

Value Derived From : Dim_W_RESOURCE_HD_ID.POSTAL_CODE

Resource

Location - (Resource)

State/Province Code

Dimension

The state abbreviation for this Location

Value Derived From : Dim_W_RESOURCE_HD_ID.STATE_CODE

Resource

Location - (Resource)

State/Province Name

Dimension

The state name for this Location

Value Derived From : Dim_W_RESOURCE_HD_ID.STATE_NAME

 

 

 

 

 

 

Time Folder

 

 

 

 

 

Time

Interval

 

 

Interval

 

Time

Interval

Interval End Date

Dimension

The end date of the Interval (1/8/2013 12:00am)

Value Derived From : Dim_W_INTERVAL_D_Interval.END_DATE

Time

Interval

Interval Name

Dimension

Interval Name (2013-W01)

Value Derived From : Dim_W_INTERVAL_D_Interval.INTERVAL_NAME

Time

Interval

Interval Start Date

Dimension

The start date of the Interval (1/1/2013 12:00am)

Value Derived From : Dim_W_INTERVAL_D_Interval.START_DATE

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Fact - Primavera - Burn Down Folder

 

 

 

 

 

Fact - Primavera - Burn Down

Metrics

 

 

Metrics

 

Fact - Primavera - Burn Down

Metrics

Actual Reported Finish (Yesterday)

Fact

The number of activities whose Actual Finish date was one day ago

Value Derived From : Fact_W_ACTIVITY_WORK_DOWN_HF_WDAct.YDA_REPORTED_COMPLETE_CNT

Fact - Primavera - Burn Down

Metrics

Actual Reported Starts (Yesterday)

Fact

The number of activities whose Actual Start date was one day ago

Value Derived From : Fact_W_ACTIVITY_WORK_DOWN_HF_WDAct.YDA_REPORTED_START_CNT

Fact - Primavera - Burn Down

Metrics

Baseline Completed Count

Fact

The number of activities in Burn Down snapshot that are completed during this time interval

Value Derived From : Fact_W_ACTIVITY_WORK_DOWN_HF_WDAct.BASE_COMPLETE_CNT

Fact - Primavera - Burn Down

Metrics

Baseline In Progress Count

Fact

The number of activities in Burn Down snapshot that are in progress during this time interval

Value Derived From : Fact_W_ACTIVITY_WORK_DOWN_HF_WDAct.BASE_IN_PROGRESS_CNT

Fact - Primavera - Burn Down

Metrics

Baseline Not Started Count

Fact

The number of activities in Burn Down snapshot that are not started during this time interval

Value Derived From : Fact_W_ACTIVITY_WORK_DOWN_HF_WDAct.BASE_NOT_START_CNT

Fact - Primavera - Burn Down

Metrics

Baseline Planned Finish Date

Fact

Activity Planned Finish Date as of baseline(T-0) date

Value Derived From : Fact_W_ACTIVITY_WORK_DOWN_HF_WDAct.BL_PLANNED_FINISH_DATE

Fact - Primavera - Burn Down

Metrics

Completed Count

Fact

The number of activities that are completed during this time interval

Value Derived From : Fact_W_ACTIVITY_WORK_DOWN_HF_WDAct.COMPLETE_CNT

Fact - Primavera - Burn Down

Metrics

Emergent Remaining Count

Fact

The number of remaining In Progress and Not Started activities that did not exist in the Burn Down snapshot

Value Derived From : Fact_W_ACTIVITY_WORK_DOWN_HF_WDAct.EMERGENT_REMAINING_CNT

Fact - Primavera - Burn Down

Metrics

In Progress Count

Fact

The number of activities that are in progress during this time interval

Value Derived From : Fact_W_ACTIVITY_WORK_DOWN_HF_WDAct.IN_PROGRESS_CNT

Fact - Primavera - Burn Down

Metrics

Emergent Count

Fact

The number of activities added that are not in Burn Down snapshot

sum(Fact_W_ASSIGNMENT_WORK_DOWN_HF_WDA.EMERGENT_REMAINING_CNT)

Fact - Primavera - Burn Down

Metrics

Non-Emergent Remaining Count

Fact

The number of remaining In Progress and Not Started activities that existed in the Burn Down snapshot

Value Derived From : Fact_W_ACTIVITY_WORK_DOWN_HF_WDAct.NON_EMERGENT_REMAINING_CNT

Fact - Primavera - Burn Down

Metrics

Not Scheduled and Completed Count

Fact

The number of activities that were not scheduled to be completed based on the Burn Down snapshot and were actually completed during this time interval

Value Derived From : Fact_W_ACTIVITY_WORK_DOWN_HF_WDAct.NOT_SCHEDULED_COMPLETED_CNT

Fact - Primavera - Burn Down

Metrics

Not Started Count

Fact

The number of activities that are not started during this time interval

Value Derived From : Fact_W_ACTIVITY_WORK_DOWN_HF_WDAct.NOT_START_CNT

Fact - Primavera - Burn Down

Metrics

Schedule Freeze Planned Finish Date

Fact

Activity Planned Finish Date as of Schedule Freeze date

Value Derived From : Fact_W_ACTIVITY_WORK_DOWN_HF_WDAct.TF_PLANNED_FINISH_DATE

Fact - Primavera - Burn Down

Metrics

Scheduled and Completed Count

Fact

The number of activities that were scheduled to be completed based on the Burn Down snapshot and were actually completed during this time interval

Value Derived From : Fact_W_ACTIVITY_WORK_DOWN_HF_WDAct.SCHEDULED_COMPLETED_CNT

Fact - Primavera - Burn Down

Metrics

Scheduled Finishes (Yesterday)

Fact

The number of activities whose Planned Finish date was one day ago

Value Derived From : Fact_W_ACTIVITY_WORK_DOWN_HF_WDAct.YDA_SCHEDULED_COMPLETE_CNT

Fact - Primavera - Burn Down

Metrics

Scheduled Finishes Today

Fact

The number of activities whose Finish date is today

Value Derived From : Fact_W_ACTIVITY_WORK_DOWN_HF_WDAct.TODAY_SCHEDULED_COMPLETE_CNT

Fact - Primavera - Burn Down

Metrics

Scheduled Finishes to Date

Fact

The number of activities whose Finish date is on or before the project Data Date

Value Derived From : Fact_W_ACTIVITY_WORK_DOWN_HF_WDAct.TO_DATE_SCHEDULED_COMPLETE_CNT

Fact - Primavera - Burn Down

Metrics

Scheduled Starts (Yesterday)

Fact

The number of activities whose Planned Start date was one day ago

Value Derived From : Fact_W_ACTIVITY_WORK_DOWN_HF_WDAct.YDA_SCHEDULED_START_CNT

Fact - Primavera - Burn Down

Metrics

Scheduled and Not Completed Count

Fact

The number of activities that were scheduled to be completed based on the Burn Down snapshot and were not completed during this time interval

Value Derived From : Fact_W_ACTIVITY_WORK_DOWN_HF_WDAct.SCHEDULED_NOT_COMPLETED_CNT

Fact - Primavera - Burn Down

Metrics

Update Time

Fact

The database time this ETL run started

Value Derived From : Fact_W_ACTIVITY_WORK_DOWN_HF_WDAct.UPDATE_TS

Fact - Primavera - Burn Down

Units

 

 

Units

 

Fact - Primavera - Burn Down

Units

Actual Period Units

Fact

The actual number of units incurred of current period

Value Derived From : Fact_W_ASSIGNMENT_WORK_DOWN_HF_WDA.ACTUAL_PERIOD_UNITS

Fact - Primavera - Burn Down

Units

Actual Units

Fact

The actual number of units incurred

Value Derived From : Fact_W_ASSIGNMENT_WORK_DOWN_HF_WDA.ACTUAL_UNITS

Fact - Primavera - Burn Down

Units

Actual Units Burn

Fact

The actual units distributed over the activity duration

Value Derived From : Fact_W_ASSIGNMENT_WORK_DOWN_HF_WDA.ACTUAL_UNITS_BURN

Fact - Primavera - Burn Down

Units

Baseline Units

Fact

Planned Units from the Burn Down snapshot

Value Derived From : Fact_W_ASSIGNMENT_WORK_DOWN_HF_WDA.BASELINE_UNITS

Fact - Primavera - Burn Down

Units

Baseline Remaining Units Burn

Fact

The expected remaining units distributed over the activity duration based on Burn Down snapshot

sum(Fact_W_ASSIGNMENT_WORK_DOWN_HF_WDA.REMAINING_UNITS_BURN)

Fact - Primavera - Burn Down

Units

At Completion Units

Fact

The sum of the Actual Units plus Remaining Units

sum(Fact_W_ASSIGNMENT_WORK_DOWN_HF_WDA.COMPLETE_UNITS)

Fact - Primavera - Burn Down

Units

Emergent Remaining Units Burn

Fact

Emergent activity remaining units distributed over the activity duration

Value Derived From : Fact_W_ASSIGNMENT_WORK_DOWN_HF_WDA.EMERGENT_UNITS_BURN

Fact - Primavera - Burn Down

Units

Non-Emergent Remaining Units Burn

Fact

Non-Emergent activity remaining units distributed over the activity duration

Value Derived From : Fact_W_ASSIGNMENT_WORK_DOWN_HF_WDA.NON_EMERGENT_UNITS_BURN

Fact - Primavera - Burn Down

Units

Remaining Units

Fact

The remaining units of work to be performed by the resource on the activity. Calculated as Planned Units minus Actual Units.

Value Derived From : Fact_W_ASSIGNMENT_WORK_DOWN_HF_WDA.REMAINING_UNITS

Fact - Primavera - Burn Down

Units

Remaining Units Burn

Fact

The remaining units distributed over the activity duration

Value Derived From : Fact_W_ASSIGNMENT_WORK_DOWN_HF_WDA.REMAINING_UNITS_BURN

Related Topics

P6 EPPM Subject Areas

P6 - Activity / Primavera Activity

P6 - Activity History / Primavera - Activity History

P6 - Activity Period Actuals / Primavera - Activity Period Actuals

P6 - Project History / Primavera - Project History

P6 - Resource Assignment / Primavera - Resource Assignment

P6 - Resource Assignment History / Primavera - Resource Assignment History

P6 - Resource Period Actuals / Primavera - Resource Period Actuals

P6 - Resource Utilization / Primavera - Resource Utilization

P6 - Role Utilization / Primavera - Role Utilization

P6 - Spread Snapshot History / Primavera - Spread Snapshot History

P6 - Work Planning / Primavera - Work Planning



Last Published Friday, December 8, 2023