Activity Sheet Sub-Node

The Activity Sheet sub-node contains a list of activity sheets (including the System Activity Sheet), and they are all listed in the Activity Sheets log or window.

You can have multiple activity sheets.

You can create User-Defined Reports (UDRs) from the Activity Sheet Data Elements (DEs).

The system uses the following schedule types to determine the activity schedule when sending activity data to the Cash Flow:

Note: The Cash Flow properties will be displayed based on the activity sheet schedule type.

Type

Description

Resource

The Activity Sheet receives the entire duration based information from P6

The Activity Sheet receives the entire resource assignment related information

(Not always) The Activity Sheet receives the entire cost related information

The Activity Sheet is available as a source for Cash Flow and Cost Sheet

The Activity Sheet has all cost related feature (Assign rate sheet and Recost)

The Activity Sheet is available for Earned Value Analysis

Cost

The Activity Sheet receives the entire duration based information from P6

The Activity Sheet receives the entire resource assignment related information

The Activity Sheet receives the entire cost related information

The Activity Sheet is available as a source for Cash Flow and Cost Sheet

The Activity Sheet does not have any cost related feature (Assign rate sheet and Recost)

The Activity Sheet is available for Earned Value Analysis

The Activity Sheet is available for Earned Value Analysis

Note: The system uses the data directly from P6 and does not perform any calculations for a cost loaded schedule.

Duration (without 'Based')

The Activity Sheet receives duration based information from P6

(Not always) The Activity Sheet receives resource assignment related information

(Not always) The Activity Sheet receives cost related information

The Activity Sheet is not available as a source for Cash Flow and Cost Sheet

The Activity Sheet does not have any cost related feature (Assign rate sheet and Recost)

The Activity Sheet is not available for Earned Value Analysis

The following explain the Activity Sheets log or window elements, followed by information regarding manual activity sheets.

See Also

Activity Manager

Bulk Assigning WBS Code to Different Activities

Link Activities (Adding Dependencies)

Manual Activity Sheet Gear Menu

Manual Activity Sheet Start Date, Finish Date, and Duration

Manual Activity Sheet and CSV Template

Manual Activity Sheet Categories

Manual Activity Sheet (Schedule Types)

Manual Activity Sheet Dates

Activity Sheet User Defined Report (UDR)

Roll Up Activity Sheet to Cost Sheet

Importing Manual Activity Sheet

In This Section

Activity Sheets Log and Manual Activity Sheets

Activity Sheets Log (Toolbar Options)

Activity Sheets Log (Columns)

Activity Sheets Log (Manual Activity Sheet Gear Menu)

Activity Sheets Log (Manual Activity Sheet Properties Tabs)

Creating Manual Activity Sheet

Manual Activity Sheet