Activity Sheet Sub-Node
The Activity Sheet sub-node contains a list of activity sheets (including the System Activity Sheet), and they are all listed in the Activity Sheets log or window.
You can have multiple activity sheets.
You can create User-Defined Reports (UDRs) from the Activity Sheet Data Elements (DEs).
The system uses the following schedule types to determine the activity schedule when sending activity data to the Cash Flow:
Note: The Cash Flow properties will be displayed based on the activity sheet schedule type.
Type | Description |
---|---|
Resource | The Activity Sheet receives the entire duration based information from P6 The Activity Sheet receives the entire resource assignment related information (Not always) The Activity Sheet receives the entire cost related information The Activity Sheet is available as a source for Cash Flow and Cost Sheet The Activity Sheet has all cost related feature (Assign rate sheet and Recost) The Activity Sheet is available for Earned Value Analysis |
Cost | The Activity Sheet receives the entire duration based information from P6 The Activity Sheet receives the entire resource assignment related information The Activity Sheet receives the entire cost related information The Activity Sheet is available as a source for Cash Flow and Cost Sheet The Activity Sheet does not have any cost related feature (Assign rate sheet and Recost) The Activity Sheet is available for Earned Value Analysis The Activity Sheet is available for Earned Value Analysis Note: The system uses the data directly from P6 and does not perform any calculations for a cost loaded schedule. |
Duration (without 'Based') | The Activity Sheet receives duration based information from P6 (Not always) The Activity Sheet receives resource assignment related information (Not always) The Activity Sheet receives cost related information The Activity Sheet is not available as a source for Cash Flow and Cost Sheet The Activity Sheet does not have any cost related feature (Assign rate sheet and Recost) The Activity Sheet is not available for Earned Value Analysis |
The following explain the Activity Sheets log or window elements, followed by information regarding manual activity sheets.
See Also
Bulk Assigning WBS Code to Different Activities
Link Activities (Adding Dependencies)
Manual Activity Sheet Gear Menu
Manual Activity Sheet Start Date, Finish Date, and Duration
Manual Activity Sheet and CSV Template
Manual Activity Sheet Categories
Manual Activity Sheet (Schedule Types)
Activity Sheet User Defined Report (UDR)
Roll Up Activity Sheet to Cost Sheet
Importing Manual Activity Sheet
In This Section
Activity Sheets Log and Manual Activity Sheets
Activity Sheets Log (Toolbar Options)
Activity Sheets Log (Manual Activity Sheet Gear Menu)
Activity Sheets Log (Manual Activity Sheet Properties Tabs)
Creating Manual Activity Sheet