Assigning Resource Curves to Resource or Role Assignments from the Resources Assignments Page
You can assign a resource distribution curve to any resource or role assignment on activities with a duration type of Fixed Duration and Units/Time or Fixed Duration & Units.
To assign a resource curve:
- Click Resources.
- On the Resources navigation bar, click Assignments.
- On the Assignments page:
- Display the Curves column if it is not visible on the table. To display the Curves column, click Customize View and click Columns, expand the General grouping and double-click Curve to move it to the Selected Columns list.
- On the Assignments page:
- Click the row with the resource or role.
- Double-click the Curve field, and clickSelect .
- In the Select Curves dialog box, choose a curve and click OK.
- On the Assignments page, click Save.
Tips:
- You can also assign resource curves to resource or role assignment from the Activities page.
Related Topics
Assigning a Resource to a Role
Assigning a Role Team to a Role
Assigning a Role to a Role Team
Assigning a Role to a Resource
Assigning a Resource Team to a Resource
Assigning Calendars to Resources
Configuring Timesheet Reporting for Resources
Assigning a Resource to a Resource Team
Assigning Resource Curves to Resource or Role Assignments from the Activities Page
Last Published Tuesday, March 26, 2024