Assigning Resource Rates
Use this procedure to assign rates to resources. You can assign multiple rates to resources to reflect price changes over time. For example, suppose the price per unit for a group of resources was $20.00 per hour for the months January through June, but the price rate increases to $30.00 starting in July through December. You can assign time-varying rates for resources to more accurately determine total resource (and activity) costs.
To assign resource rates:
- Click Resources.
- On the Resources navigation bar, click Administration.
- On the Administration page, click the Resources tab.
- On the Resources tab:
- Click a resource.
- Click the Units and Prices detail window.
- In the Units and Prices detail window:
- Click Add.
- In the Effective Date field, double-click to open the calendar and choose a date and time to start the new rate.
- In the Max Units/Time field, double-click and type the maximum work units per time for this resource.
- In the appropriate price fields, double-click and type an amount. The default time period is price per hour unless you specify another time period.
- Click Save.
Related Topics
Assigning a Resource to a Role
Assigning a Role Team to a Role
Assigning a Role to a Role Team
Assigning a Role to a Resource
Assigning a Resource Team to a Resource
Assigning Calendars to Resources
Configuring Timesheet Reporting for Resources
Assigning Resource Curves to Resource or Role Assignments from the Resources Assignments Page
Assigning a Resource to a Resource Team
Last Published Tuesday, March 26, 2024