Running the Completions Update COBOL/SQR Process (SFPDCDRV)

The Prdn Compl/Scrap (SFPDCDRV) process (Production Completions and Scrap process) updates completions transactions that are staged by other processes, such as Edit Components updates, production completions, or subcontracted completions recorded through electronic data collection. In addition, you run this process to update production quantities for production schedule completions and scrap. You run this process if you selected Stage Compltns/Putaway on Save as the completions action on the Record Completions/Scrap page.

Page Used to Run the Completions Update COBOL/SQR Process (SFPDCDRV)

Page Name Definition Name Usage

Prdn Cmpl/Scrap Page

BCT_MG_REQCOMP

Update completions transactions that are staged by other processes and for production schedules.

Prdn Cmpl/Scrap Page

Use the Prdn Cmpl/Scrap page (BCT_MG_REQCOMP) to update completions transactions that are staged by other processes and for production schedules.

Navigation:

  • Production Control, and then Process Production, and then Complete Production, and then Process Completions and Scrap

  • SCM Integrations, and then Process Transactions, and then Manufacturing, and then Process WO Completions

Field or Control Description

Unit and Request ID

Enter values for this process.

Run

Click to run this request. Process Scheduler runs the Completions/Scrap Update process at user-defined intervals.