Completing the Planning Subtab

Use the following steps to complete the Planning subtab.

To complete the planning subtab:

  1. Click the Planning subtab.

  2. In the Rates section, enter a Std Rate (Min/Unit) that matches the NetSuite routing record run rate.

    NetSuite populates the Std Rate (Unit/Hr) field when the manufacturing work bench record saves.

  3. Enter a Unit of Measure.

  4. In the Lead Time and Off Sets section, enter a Setup Time (Min) that matches the NetSuite routing record setup time in minutes.

  5. To determine how to schedule this operation to lag behind its predecessor, select a Lag Type from the list.

  6. In the Lag Value field, enter either the number of minutes or units to quantify the lag offset.

    Units should correspond to the selected lag type.

  7. In the Hold Time (Min) field, enter the number of minutes that the asset should remain unavailable following a production run.

  8. In the Batching section, in the Batch Minimum field, enter the smallest batch value that can be produced.

  9. In the Batch Maximum field, enter the largest batch value that can be produced.

    Note:

    Batch minimum and maximum values must be greater than zero and in the same units as the assembly stock unit of measure.

  10. In the Incremental Qty field, enter the incremental batch size to step from a minimum batch to a maximum batch.

    Use this value to determine the last batch size needed to fulfill a work order quantity.

  11. If multiple batches can be processed at the same time, enter the number of Concurrent Assets (Split Order) allowed to run on a single work order.

    The value must not exceed the total number of assets associated with the work center or this workbench record, whichever is less.

    Note:

    Do not use the Concurrent Assets (Split Order) field independently. You should use the field in conjunction with other batch fields.

  12. Click Save.

Related Topics

Completing the Assets Subtab
Completing the Labor Requirement Subtab
Completing the Work Instructions Subtab
Completing the Quality / Inspection Subtab
Creating Manufacturing Work Benches

General Notices