Recording Labor

Labor represents the amount of human resources (man hours) used to produce goods and services during a manufacturing operation.

To record labor:

  1. Go to Advanced Manufacturing > Data Collection > Enter Results/Loss/Downtime/Labor.

  2. Click the Labor subtab.

  3. Enter the time the labor resource was assigned to the operation in the Start Time field.

    Use the 7/11/2020 7:25:04 am format.

  4. Enter the total labor hours to charge against the operation in the Duration (Hrs) field.

  5. Select the Labor Code.

    For example, general assembler, quality engineer, or supervisor.

  6. Enter the total number of resources the operation used in the Resource Count field.

  7. (Optional) Select the Asset Name.

    If you do not select an asset, NetSuite uses the asset the work order was scheduled for.

  8. (Optional) Select the name of the Employee who entered the data.

  9. Click Save.

    This information is tracked and associated with the work order.

Related Topics

Tracking Production Results
Recording Material Loss
Recording Downtime
Using the Scanner to Enter Data
Entering Tablet Data
Collecting Data