Implementing Engineering Change Orders

If you have not set the feature’s Implement Engineering Change Order Upon Final Approval preference, an ECO administrator must manually implement approved ECO records.

To implement approved engineering change orders:

  1. Go to Lists > Implement Engineering Change Order (Administrator).

  2. Use filters to search for approved ECO records:

    • Use the calendar to search by effective date range. Today’s date is the default date.

    • Select a subsidiary.

  3. The page lists matching records, if any.

    • To implement all records in the list, click Mark All. To implement only specific ECO records, check the Select box for the record.

    • Use the pagination controls as needed to make selections.

  4. Click Implement.

    To view the implementation status of an ECO record, see Viewing Implementation Status.

Note:

Set the Implement Engineering Change Order Upon Final Approval preference to automatically implement approved ECOs. See Setting Engineering Change Order Preference.

Related Topics:

Creating Engineering Change Orders
Approving or Rejecting Engineering Change Orders
Resubmitting Engineering Change Orders for Approval
Viewing Approval History
Using Engineering Change Order

General Notices