Inbound Shipment Purchase Order Billing Examples

You can bill either the purchase order or the inbound shipment first. The following examples show you how.

Billing the Purchase Order First

In this example, you bill the items that aren't on the inbound shipment first. Then you bill the items on the shipment.

To bill the purchase order before the inbound shipment:

  1. Create a purchase order (PO) with a total item quantity of 10.

  2. Create an inbound shipment that includes 8 of the items from the PO.

  3. Receive all 8 items on the inbound shipment. You can now bill those items.

  4. Bill the PO for the 2 items that aren't on the inbound shipment.

  5. Bill the entire Inbound shipment with a quantity of 8 or more.

Billing the Inbound Shipment First

In this example, you bill the items on the inbound shipment first. Then you bill the remaining items on the purchase order.

To bill the inbound shipment before the purchase order:

  1. Create a purchase order (PO) with a total item quantity of 10.

  2. Create an inbound shipment that includes 8 of the items from the PO.

  3. Receive all 8 items on the inbound shipment. You can now bill those items.

  4. Bill the inbound shipment for all 8 items.

  5. Bill the PO for the 2 remaining items that aren't on the inbound shipment.