Setting a Default Scheduling Method

A default production scheduling method appears by default in the Scheduling Method field on work orders created manually and by automated supply planning.

To set default scheduling method:

  1. Go to Setup > Manufacturing > Manufacturing Preferences.

  2. In the Production Planning and Scheduling Allocation section, Default Scheduling Method field, choose either Forward or Backward.

    This field defaults to the Forward scheduling.

  3. Click Save.

This method you select automatically completes work orders. However, you can change the method on individual orders with a status of Planned or Released.