Backward Scheduling

When you use the backward scheduling method for production planning, you set the production end date. This is the date you need to have the completed items. Based on data from the associated routing and related work center calendar, NetSuite calculates the time, materials, and resources required to complete all operations. NetSuite determines the production start date and time based on these calculations.

For example, you need to schedule an order of widgets that requires two operations to complete a production run. Each operation requires 1 day of setup time and 10 days of production time. Operation 1 must be complete before Operation 2 can start. These production requirements appear in the following illustration:

Diagram of backward scheduling workflow.

When you enter the items completed date, NetSuite calculates the day work must begin to complete production on time. When a work order is created by a supply plan, NetSuite schedules work so that the last operation is completed before the due date. The due date time is 00:01 AM. Therefore, the last operation on the work order is scheduled for completion by 11:59 PM on the day before the due date.

The time displayed for each operation is based on work hours set for each work center. For more information, see Creating Manufacturing Work Centers or Groups.

Screenshot of a sample routing operation.

Planners who use the Backward Scheduling method can reduce waste of manufacturing resources because NetSuite calculates start dates automatically. Work order production is scheduled to start as late as possible, giving planners flexibility to cancel or change an order.

Note:

The NetSuite planning engine calculations may set a production start date in the past, depending on the end date entered.

Production work is not automatically reallocated based on resource capacity. After work orders are created, you may need to assess resource assignments.

When Backward Scheduling is used as the default scheduling method, the production end date on generated work orders is determined using the following factors:

Related Topics

Production Scheduling Methods Overview
Setting a Default Scheduling Method

General Notices