2.3 Electrical Power Requirements

The Oracle PCA can operate effectively over a wide range of voltages and frequencies. However, it must have a reliable power source. Damage might occur if the ranges are exceeded. Electrical disturbances such as the following might damage the system:

  • Fluctuations caused by brownouts

  • Wide and rapid variations in input voltage levels or in input power frequency

  • Electrical storms

  • Faults in the distribution system, such as defective wiring

To protect your system from such disturbances, you should have a dedicated power distribution system, power-conditioning equipment, as well as lightning arresters or power cables to protect from electrical storms.

Each rack has two pre-installed power distribution units (PDUs). The PDUs accept different power sources. You must specify the type of PDU that is correct for your data center.

Table 2.4 lists the PDU low-voltage requirements.

Table 2.4 PDU Types and Specifications

Item

15kVA - type 6440A

15kVA - type 6441A

15kVA - type 6442A

22kVA - type 7100873

22kVA - type 7100874

24kVA - type 6444A

24kVA - type 6445A

Region

North and South America, Japan and Taiwan

EMEA and APAC (except Japan and Taiwan)

North and South America, Japan and Taiwan

North and South America, Japan and Taiwan

EMEA and APAC (except Japan and Taiwan)

North and South America, Japan and Taiwan

EMEA and APAC (except Japan and Taiwan)

Number of inputs

1

1

3

3

3

2

2

Source voltage

200-220V

220/380 - 240/415VAC

200-240V

200-240V

200-240V

200-220V

220/380 - 240/415VAC

Frequency

50/60 Hz

50/60 Hz

50/60 Hz

50/60 Hz

50/60 Hz

50/60 Hz

50/60 Hz

Max. line current

40A

21A

24A

36.8A

32A

34.6A

16A

Phase current

23A

21A

N/A

N/A

32A

20A

16A

Recommended circuit breaker

50A

25A

30A

50A

30A

50A

25A

Outlets

42 x C13 6 x C19

42 x C13 6 x C19

42 x C13 6 x C19

42 x C13 6 x C19

42 x C13 6 x C19

42 x C13 6 x C19

42 x C13 6 x C19

Outlet groups

6

6

6

6

6

6

6

Max. group current

20A

20A

20A

20A

20A

20A

18A

Output voltage

200-240V

220-240V

200-240V

200-240V

200-240V

220-240V

200-240V

Data center receptacle

3ph 3W + ground 60A IEC60309

3ph 4W + ground 32A IEC60309 5P 6h 400V

1ph 2W + ground 30A NEMA L6-30

1ph 2W + ground 50A Hubbell CS8265C

1ph 2W + ground 32A IEC60309 3P 6H 230V

3ph 3W + ground 60A IEC60309

3ph 4W + ground 32A IEC60309 5P 6h 400V


2.3.1 Facility Power Requirements

Electrical work and installations must comply with applicable local, state, or national electrical codes. Contact your facilities manager or qualified electrician to determine what type of power is supplied to the building.

To prevent catastrophic failures, design the input power sources to ensure adequate power is provided to the power distribution units (PDUs). Use dedicated AC breaker panels for all power circuits that supply power to the PDU. When planning for power distribution requirements, balance the power load between available AC supply branch circuits. In the United States and Canada, ensure that the overall system AC input current load does not exceed 80 percent of the branch circuit AC current rating.

PDU power cords are 4 meters (13.12 feet) long, and 1 to 1.5 meters (3.3 to 4.9 feet) of the cord will be routed within the rack cabinet. The installation site AC power receptacle must be within 2 meters (6.6 feet) of the rack.

2.3.2 Circuit Breaker Requirements

To prevent catastrophic failures, the design of your power system must ensure that adequate power is provided to all of the compute nodes. Use dedicated AC breaker panels for all power circuits that supply power to the compute nodes. Electrical work and installations must comply with applicable local, state, or national electrical codes. Compute nodes require electrical circuits to be grounded to the Earth.

In addition to circuit breakers, provide a stable power source, such as an uninterruptable power supply (UPS) to reduce the possibility of component failures. If computer equipment is subjected to repeated power interruptions and fluctuations, then it is susceptible to a higher rate of component failure.

Note

Circuit breakers are supplied by the customer. One circuit breaker is required for each power cord.

2.3.3 Grounding Guidelines

The cabinets for the Oracle PCA are shipped with grounding-type power cords (three-wire). Always connect the cords to grounded power outlets. Because different grounding methods are used, depending on location, check the grounding type, and refer to documentation, such as IEC documents, for the correct grounding method. Ensure that the facility administrator or qualified electrical engineer verifies the grounding method for the building, and performs the grounding work.