Go to main content

SPARC T7-2 Server Installation Guide

Exit Print View

Updated: July 2017
 
 

Cabling Requirements

Prior to cabling and powering-on the server, gather the following network information:

  • Netmask

  • IP address for the SP

  • Gateway IP address

At a minimum, you must connect cables to these ports before powering-on the server for the first time:

  • SP SER MGT port

  • SP NET MGT port

  • At least one system on-board Ethernet network port

  • Power cables to the power supply inlet ports

Related Information