Facility Power Checklist
Complete the following checklist to ensure that the facility power requirements are
met for the data center in which the server is installed:
|
|
|
|
|
Do you know the required operating voltage and electric
current level of the server?
|
|
|
|
|
Are enough power outlets provided within 2 meters (6.5
feet) for each rack?
|
|
|
|
|
Do the power outlets have appropriate socket receptacles?
|
|
|
|
|
Will optional ground cables be attached to the rack?
|
|
|
|
|
Are the circuit breakers for the equipment suitable in terms of
voltage and current-carrying capacities?
|
|
|
|
|
Does the power frequency meet the equipment specifications?
|
|
|
|
|
Will system power be delivered from two separate power
grids?
|
|
|
|
|
Is there a UPS to power the equipment?
|
|
|
|
|
Do you have the minimum required power sources to support the
power load for the new hardware? Use kilowatt (kW)/kilovolt (kVA) to
express power load.
|
|
|
|
|
|