Defining Planning Parameters
From the Planning Parameters window, you can enable planning functions. You can also define and update execution options and default values that affect other functions in Oracle Master Scheduling/MRP and Supply Chain Planning.
To define and update the enable dates and default parameters:
Note: It is not necessary to check this box when running the Memory-based Planning Engine. However, you may still wish to check this box for absolute data consistency.
The planning process does not consider any demand from forecasts within the demand time fence, but does consider demand from sales orders.
Attention: You must enter safety stock information for your items before Oracle Master Scheduling/MRP calculates safety stock for the items. See: Defining Items.
If you do not check this, the planning process does not recommend the rescheduling of purchase orders, and may over plan the item because it creates additional planned orders.
If you do not check this, the planning process plans the items as if no planning time fences exist.
If you do not check this, the planning process does not recommend rescheduling of work orders, and may over plan the item because it creates additional planned orders.
If you do not check this, the planning process does not consider material reservations for the item and may consider the on-hand quantity for the item available for any demand.
Operation start date: Schedule material to arrive in inventory for availability on the start date of a specific operation in the manufacturing process.
Order start date: Schedule material to arrive in inventory for availability on the work in process order start date.
Repetitive planning uses a series of repetitive planning periods (defined as repetitive planning horizon and repetitive planning buckets) to level the production rate over time. When planning the repetitive part, all the demand is grouped by the number of days you specify, and the supply is averaged out over the period.
2. Select the type of dates you want to use:
Work dates: Calculate the repetitive planning periods using workdays. This allows the periods to shift out due to holidays. If a start date falls on a holiday, the start date is changed to the next valid working day. Each repetitive planning period consists only of valid working days.
Calendar dates: Calculate the repetitive planning periods using calendar days. This allows you to fix the length of the periods regardless of the timing of holidays (non-workdays). A repetitive planning period can start on a holiday and include holidays.
If, during the planning process, you change the repetitive planning anchor date, this date is updated to the start date of the first repetitive planning period.
For example, you might enter 5 to signify that the first repetitive planning horizon is grouped into "buckets" of 5 days.
5. Enter the number of workdays for the first repetitive horizon in First Horizon.
For example, you might enter 30 to signify the first 30 days of production are grouped into the first repetitive bucket size you specify.
For example, you might enter 10 to signify that the second repetitive planning horizon is grouped into "buckets" of 10 days.
7. Enter the number of workdays for the second repetitive horizon in Second Horizon.
For example, you might enter 60 to signify the next 60 days of production are grouped into the second repetitive bucket size you specify.
For example, you might enter 40 to signify that the rest of the repetitive planning horizon production is grouped into "buckets" of 40 days.
See Also
Overview of Time Fence Planning
Overview of Material Requirements Planning
Setting Up Project MRP in Master Scheduling/MRP and Supply Chain Planning