New Features in MRP and Supply Chain Planning Release 10.7.0.16SC

New features in this release include:

Add Firm Planned Orders for MPS Items

You can now modify or add an order for an MPS Planned item in the Planner Workbench, for MPS plans generated with the Memory-based Planning Engine. See: Creating Firm Planned Orders.

Byproduct Planning

For plans generated with the Memory-based Planning Engine, you can now plan byproducts, and include byproduct planning information in the following reports:

Forecast Consumption Cutoff Date

You can specify a cutoff date for forecast consumption, allowing you to plan only to forecast after the cutoff date.

Forecast Interface

To support project manufacturing in a future release, we have included project and task references in the forecast interface.

To support Oracle Automotive in a future release, we have added support for online processing and the ability to create, delete, and replace all existing forecast entries within a forecast designator or delete all existing forecast entries within a forecast designator.

Oracle Automotive Support

To support Oracle Automotive in a future release, Oracle Master Scheduling/MRP and Supply Chain Planning has added fields related to Oracle Automotive in the following window:

Window Fields added
Implement Property Sheet Schedule Group, Build Sequence

Phantom Bills of Material

With the Memory-based Planning Engine, the planning process can determine if an item is a phantom bill (phantom assembly), then blow through the phantom to create planned orders or suggested repetitive schedules for component items. See: Item and Bill of Material Attributes.

Project Manufacturing Support (BETA)

To support project manufacturing in a future release, Oracle Master Scheduling/MRP and Supply Chain Planning has added fields related to project manufacturing in the following windows:

Window Fields added
Assign Project Parameters Project Number, Planning Group, Costing Group, WIP Acct Class, Seiban Number Flag, Project Name; also new button "New"
Define Seiban Numbers Seiban Number, Seiban Name, Operating Unit; also new buttons, "New" and "Parameters"
Item Forecast Entries Project Number, Task Number
Item Master Demand Schedule Entries Project Number, Task Number
Item Master Production Schedule Entries Project Number, Task Number
Plan Options new region and check box "Pegging" with two fields: "Reservation Level" and "Hard Pegging Level"
Plan Status new region and check box "Pegging" with two fields: "Reservation Level" and "Hard Pegging Level"
Supply/Demand Project Number, Task Number
Implement Property Sheet Project Number, Task Number
Horizontal Plan new poplist allowing you to display the material plan in horizontal buckets for a single task, project, planning group, or common supply
Enterprise View new poplist allowing you to display the multi-plant material plan in horizontal buckets for a single task, project, planning group, or common supply
Planning Group QuickCodes all fields
Project On Hand Item, Org, Quantity, Subinventory, Project Number, Task Number
Full Pegging (Object Navigator) Project Number, Task Number
Special Menu Onhand

Notes

Changes to reports

Master Schedule Detail Report

Display project and task number for schedule entries.

Planning Detail Report

Display project and task number for bucketless display of material plan.

Planned Order Report

Display project and task number for each planned order.

Order Reschedule Report

Display project and task number for all orders.

Late Order Report

Display project and task number for all orders.

Online Planner (BETA)

To support a future release, Oracle Master Scheduling/MRP and Supply Chain Planning has added a region ("Net Change Replan") to the replace the Net Change Replan button, and a new window ("On-Line Planner Status") in the Planner Workbench.

The Online Planner supports replanning decisions in large and dynamic industrial organizations. It delivers a fast, intuitive, and user-friendly tool for replanning. From the Planner Workbench, you can start the Online Planner for the currently loaded plan. You can then make changes to the plan and allow the Online Planner to plan all affected items. If you are satisfied with the changes, you can stop the Online Planner and implement your plan.

The Online Planner allows you to save the plan exceptions after a replan. The Planner Workbench allows you to compare the exceptions over time.

With the Online Planner, you can also make a copy of any plan, to which you can return at any stage.

Supplier Planned Inventories

To support a future release , Supply Chain Planning users can integrate supplier and customer inventory information with information from manufacturing and distribution organizations. Such information gives you an overall picture of the supply chain and provides early warning of stock-outs, swings in demand, and capacity problems.

Supply Chain Planning treats customers and suppliers as external organizations, which you can include in your sourcing strategies and ATP calculations. You can also share all relevant supply and demand information with your suppliers and customers.

See Also

New Features in MRP and Supply Chain Planning Release 10.7.0.16SC

New Features in MRP and Supply Chain Planning Release 10.6.0.15SC

New Features in MRP and Supply Chain Planning Release 10.6.0.14SC

New Features in MRP and Supply Chain Planning Release 10.6.0.13SC