Permissions Setting for Activity Sheet

Note: If the user gets any of the permissions below, then the user can access the Activity Sheet node, in the User mode.

To enable the users create, modify, and view the activity sheets, where the user can manually create project schedules, go to the shell, Admin mode and:

  1. From the left-hand Navigator, click Access Control.
  2. In the Access Control log, click to expand the User Mode Access.
  3. Click Activity Manager to expand.
  4. Click Activity Sheet to open the Permissions Setting for: Activity Sheet window.
  5. Select from the following permission settings:

See Also

Setting up the Schedule Manager

Additional Options for Setting Up the Schedule Manager

Importing an Activity Attribute Form

Create Schedule Sheet Templates

Deleting Schedule Sheets

Grant Schedule Manager and Custom Calendar Permissions to Users

Refresh Schedule Sheet Data

Updating Schedule Sheet Properties from Templates

Update Schedule Sheet Activities from Templates

Importing Schedule Files

Scope Management Setup

About Activity-level Editing

Activity Sheet Permissions in the System Activity Sheet Permissions Tab

Permissions for the System WBS Sheet